Proyecto Touro copper project, Spain

18th May 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Proyecto Touro copper project.

Location
The project is located in the A Coruña province of the Galicia region, in north-west Spain.

Client
Atalaya Mining.

Project Description
A prefeasibility study (PFS) on Atalaya Mining’s proposed Proyecto Touro copper project has determined that it will be profitable. It comprises several deposits of which four – Arinteiro, Vieiro, Bama and Brandelos – have previously been mined; and two – Monte de las Minas and Arca – have not been mined.

The project has proven and probable reserves of 90.91-million tonnes grading 0.43% copper, for contained copper of 392 000 t.

The PFS envisages the construction of an openpit mine and concentrator, with average yearly production of 30 000 t of copper and 70 000 oz of silver in concentrate.

The proposed flowsheet uses conventional crushing and semiautogenous/ball mill grinding, followed by a flotation recovery circuit and concentrate thickening and filtration.

The concentrator and associated service facilities are designed for an initial Phase 1 plant of six-million tonnes a year and then a Phase 2 upgrade to increase plant throughput to ten-million tonnes a year before Year 8.

The project will use in-pit tailings disposal for a substantial part of the mine life, owing to the multiple pit mine operating plan.

During the initial years of operation, tailings will be stored in a surface tailings management facility (TMF). After Year 8, tailings will be stored in the exhausted Vieiro and Arinteiro openpits. The surface TMF will have an impervious liner and a capacity of 44-million tonnes of tailings, while the in-pit TMF will store 47-million tonnes of tailings. 

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a post-tax net present value, at an 8% discount rate of $180-million using a long-term copper price of $3/lb and an unlevered internal rate of return of 20.5%.

Value
Preproduction capital expenditure is estimated at $165-million, with an additional expansion capital estimate of $30-million in Year 8.

Duration
The project will take two years to develop and will operate for 12 years.

Latest Developments
None stated.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Atalaya Mining, tel +357 2244 2705 or email info@atalayamining.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.043 0.461s - 111pq - 2rq
Subscribe Now