Project 1 Maseve platinum mine, South Africa
Name of the Project
Project 1 Maseve platinum mine (formerly Western Bushveld Joint Venture Project 1).
Location
North West, South Africa.
Client
Development of the project has been conducted through Maseve Investments 11. As of August 31, 2015, Platinum Group Metals (PTM) subsidiary PTM RSA majority-owns this company, with 82.9%. Africa Wide Mineral Prospecting and Exploration, 100% owned by JSE-listed Wesizwe Platinum, holds the remaining 17.1%.
Project Description
The Maseve platinum mine, located about 35 km from Rustenburg, comprises projects 1, 2 and 3.
The mine plan for Project 1 has been revised. The new plan envisages the construction of a platinum mine and a concentrator to produce between 234 000 oz/y and 300 000 oz/y of combined platinum, palladium, rhodium and gold (4E) in concentrate.
During nine years of peak production, about 275 000 oz/y of 4E in concentrate will be produced from the project’s Merensky reef horizon.
The Merensky reef will be mined at widths of between 93 cm and 176 cm and the upper group two reef will be mined at widths of between 105 cm and 205 cm.
The mining and development plan includes conventional hand-held drilling equipment, electrical drills and scrapers, as well as winch cleaning, which is similar to the successful conventional mining operations at the adjacent mines.
Declines and primary access to the deposit have been designed for development using mechanised equipment.
Ore will initially be hauled out of the mine using mechanised equipment and transported by conveyor from Year 4 to the end of the mine’s 22-year life.
The concentrator has been designed and recosted, based on treating the optimal 140 000 t/m. The revised mine plan has increased this treatment rate to 160 000 t/m and, for the concentrator to treat the increased quantity of reef, the recovery has been reduced to a discount of up to 2.5% for treatment over the nominal nameplate capacity.
Jobs to be Created
Not stated.
Net Present Value/Internal Rate of Return
The project's independent feasibility model developed a post-tax net present value of $431-million at a 5% discount rate.
Value
Peak funding for the project has increased from $502-million in the first quarter of 2015 to $514-million currently.
Of the required capital cost, a fully funded $100-million for the Phase 1 surface establishment and underground decline development programme have been allocated.
Duration
Not stated.
Latest Developments
To achieve positive cash flow and maintain its working capital covenants under existing loan facilities, PTM estimates that it needs to source between C$5-million and C$15-million of additional funding.
The company has said it will weigh options, including refinancing its existing debt, issuing new debt and private or public offerings of equity, or the sale of project or property interests.
PTM has stated that its objective will be to turn the Maseve mine to positive cash flow in the first half of 2017. At November 30, PTM held $27.51-million in cash.
The production ramp-up at Maseve has been behind schedule since commissioning in April 2016, owing to poor mining contractor performance and delayed infrastructure completion.
A safety drive by the North West inspectorate branch of the Department of Mineral Resources (DMR) during the latter part of PTM’s first quarter, ended November, resulted in intermittent work stoppages at the Maseve mine, also causing a loss of some development and production.
Production in September, October, November and December was 1 823 oz platinum, 907 oz palladium, 1 237 oz rhodium and 1 509 gold. Contractor issues and the changeover of contractors and concerns raised by the DMR have been addressed, PTM has said it is once more focused on increasing mined tonnage at grade from planned blocks while reducing costs in 2017.
PTM has said that development in other blocks near the initial high-grade Block 11, with good grade thickness, is scheduled to continue during the year. The company has forecast the 12-month total output guidance for 2017 at 100 000 oz to 120 000 oz 4E.
In return for issuing 568 819 common shares, the Sprott Resource Lending Partnership and Liberty Metals & Mining Holdings have agreed to provide a waiver and amendments to their existing loan facilities to PTM to accommodate the company for the delayed production ramp-up at Maseve. The total debt owed to the two lenders amounts to C$1.15-million.
Key Contracts and Suppliers
Société Generale, Barclays Bank, Absa Capital, Standard Bank of South Africa and Caterpillar Financial (lead finance arrangers); Turnberry Projects (prefeasibility study and overall feasibility study); Wardrop Engineering (decline access); GRD Minproc (concentrator design); Grinaker-LTA Mining (vertical shaft design); Golder Associates Africa and Oryx Environmental (public consultation and environmental permitting work); DRA Mining (engineering, procurement and construction management) and JIC Mining Services (underground decline tunnels).
On Budget and on Time?
Output at Maseve is behind schedule, owing to challenges related to the ramp-up of stoping tonnes, resulting in a loss of planned revenue from operations.
Contact Details for Project Information
PTM investor and media enquiries, tel +1 604 899 5450, fax +1 604 484 4710 or email info@platinumgroupmetals.net.
Wesizwe Platinum, Sirkien van Schalkwyk, tel +27 11 994 4600, fax +27 11 994 4601 or email Sirkien@wesizwe.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation

















