Positive wellfield results keep Gunnison on pace for copper production this quarter
The Gunnison copper project, in southern Arizona, is performing better than planned, with the initial copper recovery grades exceeding feasibility study expectations, TSX- and FSE-listed Excelsior Mining reported on Wednesday.
Pregnant leach solution grade is currently measuring 0.15 g/ℓ copper in the primary recovery pond – a milestone that Excelsior achieved ahead of schedule and keeps the project on pace for copper production this quarter.
"We have the newest, most orderly, and technologically advanced in-situ recovery wellfield on the planet, and to date, it is functioning better than anticipated,” stated president and CEO Stephen Twyerould.
Acid injection is being steadily increased and is currently at about 50% of the full production rate. The 41 injection and recovery wells that comprise the production wellfield will continue to circulate mining solutions in a closed-loop system until the concentration of copper held in solution warrants processing.
Once this grade is achieved, mining solutions will then be treated through the Johnson Camp processing facilities to extract copper and produce LME grade copper cathode sheets.
First copper cathode sales are expected in the first quarter.
Excelsior last week started operations at Gunnison, which is permitted to produce 125-million pounds a year. The Environmental Protection Agency recently approved the start of mining operations through the injection of acid.
The Gunnison in-situ recovery copper extraction project is permitted to produce 125-million pounds a year of copper cathode. The feasibility study projected an after-tax net present value of $807-million and an internal rate of return of 40%, using a $2.75/lb copper price and a 7.5% discount rate.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation