https://www.miningweekly.com

Platreef Shaft 1 intersects Flatreef deposit at 780 m below surface

10th October 2018

By: Creamer Media Reporter

     

Font size: - +

Shaft 1 at Ivanplats’ Platreef project has reached the top of the high-grade Flatreef deposit at 780.2 m below surface.

This is the first time that the Platreef – a strongly mineralised, polymetallic belt that extends northward from the town of Mokopane for more than 30 km – has been intercepted by underground mining activity, Ivanplats’ parent company Ivanhoe Mines reports.

The Platreef mining team has delivered the first ore from the underground mine development to a surface stockpile for metallurgical sampling.

The estimated thickness of the mineralised reef at Shaft 1 is 26 m, with grades of platinum-group metals ranging up to 11 g/t platinum, palladium and rhodium (3E) plus gold, as well as significant quantities of nickel and copper.

The 26 m intersection is expected to yield about 3 000 t of ore that is estimated to contain more than 400 oz of platinum-group metals (PGMs).

“This is a significant milestone for Ivanplats and a tribute to the excellent work by the Platreef project team and its South African sinking contractor, Aveng Mining. We now can proudly show our stakeholders and investors Flatreef’s remarkably high-grade and thick, flat-lying orebody that is ideal for safe, underground, bulk-scale, mechanised mining,” says Ivanplats MD Dr Patricia Makhesha.

Ivanplats adds that the mine plan calls for the addition of large, mechanized mining equipment, including 14 t and 17 t load-haul-dump machines and 50 t haul trucks to support the planned long-hole mining method.

The Flatreef deposit has a strike length of 6 km and lies within a flat to gently dipping portion of the Platreef mineralised belt at relatively shallow depths of 700 m to 1 200 m below surface.

A July 2017 definitive feasibility study estimated that the Platreef project, which is adjacent to Anglo American Platinum’s Mogalakwena mine, would initially produce 476 000 oz/y of 3E and gold, in addition to 21-million pounds a year of nickel and 13-million pounds a year of copper.

Under the current development plan, mining will start at an initial rate of four-million tonnes a year in the first phase and will be expanded to eight-million tonnes in the second phase and to 12-million tonnes in the third phase.

Meanwhile, the 750 m station at Shaft 1 has been completed. The station will provide initial underground access to the high-grade orebody and enable mine development to proceed during the construction of Shaft 2, which will become the Platreef mine’s main production shaft.

A further two stations will be developed at 850 m and 950 m below ground. Shaft 1 is expected to reach its final depth of 980 m in early 2020.

Further, Ivanplats is also making progress with the excavation of the Shaft 2 boxcut to about 29 m below surface.

The boxcut will allow for the construction of the concrete foundation for the 103-m-tall concrete headgear that will house the shaft’s permanent hoisting facilities and support the shaft collar.

Shaft 2, with an internal diameter of 10 m, will be sunk to 1 104 m below surface.

It will be equipped with two 40 t rock-hoisting skips with the capacity to hoist six-million tonnes a year of ore – the single-largest hoisting capacity at any mine in Africa. The headgear for the permanent hoisting facility was designed by Murray & Roberts Cementation.

MARKET POTENTIAL
Ivanhoe co-chairperson Robert Friedland comments that, while some investors have expressed concern about the current price of platinum, Platreef also has massive quantities of palladium, nickel and copper, as well as rhodium and gold.

“Building a new, large-scale mine such as Platreef is a capital- and time-intensive process that requires us to embrace the future, and the future we see will include a lot more electric vehicles (EVs) using batteries and fuel cells.

“We are confident that platinum, copper and nickel will be among the biggest beneficiaries of the accelerating global transition to EVs and clean energy,” he adds.

Ivanhoe owns 64% of the Platreef project through its Ivanplats subsidiary. A Japanese consortium owns a further 10% of the project, while South African empowerment partners hold a 26% interest.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (12/04/2024)
12th April 2024 By: Martin Creamer
Magazine round up | 12 April 2024
Magazine round up | 12 April 2024
12th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.123 0.156s - 105pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: