Pebble copper/gold/molybdenum/silver/rhenium project, US – update

7th May 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Pebble copper/gold/molybdenum/silver/rhenium project.

Location
South-west Alaska, US.

Project Owner/s
Pebble Limited Partnership (PLP), wholly owned by Northern Dynasty Minerals.

Project Description
The Pebble project is the world’s biggest undeveloped copper and gold resource. The project’s tonnes, grade, metallurgy and geometry have the potential to support a modern, long-life mine.

The project’s current resource estimate includes 6.44-billion tonnes in the measured and indicated categories containing 57-billion pounds of copper, 70-million ounces of gold, 3.4-billion pounds of molybdenum and 344-million ounces of silver. The inferred category of 4.46-billion tonnes contains 24.5-billion pounds of copper, 37-million ounces of gold, 2.2-billion pounds of molybdenum and 170-million ounces of silver. The deposit also contains palladium and rhenium.

The PLP is proposing to develop the Pebble copper/gold/molybdenum porphyry deposit as an openpit mine, with associated on- and off-site infrastructure, including:
• a 230 MW power plant located at the mine site,
• a 134 km transport corridor from the mine site to a port site on the west side of Cook Inlet,
• a permanent, year-round port facility near the mouth of Amakdedori Creek on Cook Inlet and
• a 303 km natural gas pipeline from the Kenai Peninsula to the Pebble project site.

The proposed mine will operate for about 20 years. This includes 14 years of mining using conventional drill-blast-shovel operations, followed by six years of milling material from a low-grade-ore stockpile. The mining rate will average 90-million tons a year, with 58-million tons of mineralised material being processed through the mill every year for an extremely low life-of-mine, waste-to-ore ratio of 0.1:1.

Mine site facilities will include an openpit mine, tailings storage facilities (TSFs), a low-grade-ore stockpile, overburden stockpiles, quarry sites, water management ponds, milling and processing facilities, as well as supporting infrastructure such as the power plant, water treatment plants, camp facilities and storage facilities.

The openpit will be developed in stages and will eventually be 1 981 m long, 1 676 m wide and between 405 m and 533 m deep. A total of 1.2-billion tons of material will be mined, including 1.1-billion tons to be processed through the mill and 100-million tons of waste rock.

Nonpotentially acid-generating (non-PAG) waste rock will be used as construction material for on-site roads and TSF embankments. 

A small amount of waste rock considered non-PAG will be stored in a lined low-grade-ore stockpile until mine closure, at which time it will be back-hauled to the openpit for permanent subaqueous storage.

Mineralised material will be processed using conventional froth flotation. On average, the process plant will produce about 600 000 t/y of copper/gold concentrate containing an estimated 287-million pounds of copper, 321 000 oz of gold, 1.6-million ounces of silver and 15 000 t/y of molybdenum concentrate containing about 13-million pounds of molybdenum.

A TSF, located in the North Fork Koktuli drainage, will store 1.1-billion tons of tailings generated over 20 years of mine operations. About 88% will be non-PAG bulk tailings; the remaining 12% will be pyritic PAG tailings, which will be stored subaqueously in a separate, fully lined cell within the TSF. Four TSF embankments, ranging from 18.3 m (east embankment) to 183 m (main embankment) in height will be developed, with centre-line or downstream construction methods used for all external embankments. A conservative 2.6:1 (horizontal:vertical) slope is targeted to ensure safety and stability under all operating conditions, including for maximum possible flood and seismic events.

Potential Job Creation
The Pebble project will directly employ about 2 000 workers during its four-year construction phase and an estimated 850 workers during its 20-year operations phase.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Capital expenditure on Pebble is estimated at between $6-billion and $8-billion.

Planned Start /End Date
Not stated.

Latest Developments
Northern Dynasty Minerals has completed an environmental, social and governance (ESG) report for the Pebble copper/gold/molybdenum/silver/rhenium.

The report addresses a range of progressive principles, practices and commitments that the company has used at Pebble over the past two decades to advance the project towards environmentally sound and socially responsible development.

“For many reasons, including the Pebble deposit’s size and significance, its location in a vast region that supports world-class fisheries, and the active campaigning of national environmental organisations, the . . .  project has been marked by public controversy and rhetoric.

“It’s unfortunate because so much of the good work done to plan, permit, develop and operate a modern copper mine at Pebble that would, in many ways, set a new standard for responsible mineral development in the US, has been obscured,” Northern Dynasty president and CEO Ron Thiessen has lamented.

The report summarises the major ESG polices, planning and engineering approaches, as well as social commitment that the company has made since acquiring the project in 2001 through to receiving a negative record of decision (RoD) from the US Army Corps of Engineers (USACE) in late 2020.

In July 2020, following two-and-a-half years of reviews by the USACE and eight federal cooperating agencies, three State cooperating agencies, the Lake and Peninsula Borough and federally recognised tribes, the final environmental impact statement from the project was published.

It found the proposed mine would not have a measurable impact on local fish populations or on the commercial, subsistence and sport fisheries that depend on them, Northern Dynasty has stated.

However, the USACE issued a negative RoD for the project, which is under appeal, in November 2020.

Key Contracts, Suppliers and Consultants
Wardrop Engineering (preliminary assessment report).

Contact Details for Project Information
PLP, tel +1 907 339 2600, fax +1 877 450 2600 or email receptionist@pebblepartnership.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.054 1.363s - 111pq - 2rq
Subscribe Now