Pebble copper/gold/molybdenum/silver/rhenium project, US – update

Image of a drill rig at the Pebble project

Photo by Northern Dynasty

4th August 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Pebble copper/gold/molybdenum/silver/rhenium project.

Location
South-west Alaska, in the US.

Project Owner/s
Pebble Limited Partnership, a subsidiary of Northern Dynasty Minerals.

Project Description
A preliminary economic assessment (PEA) published in September 2021 has provided updated production, financial and cost estimates for the proposed project.

The 2021 PEA also examines three potential mine-expansion scenarios and potential alternative strategies for gold recovery that could form the basis for future permit applications and reviews.

The proposed project envisages a 20-year openpit mining operation with a processing rate of 180 000 t/d. Life-of-mine (LoM) metal production for this scenario is estimated at 6.4-billion pounds of copper, 7.3-million ounces of gold, 300-million pounds of molybdenum, 37-million ounces of silver and 230 000 kg of rhenium.

Average metal production is forecast at 320-million pounds a year of copper, 363 000 oz/y of gold, 15-million pounds a year of molybdenum, 1.8-million ounces a year of silver and 12 000 kg/y of rhenium.

The three expansion scenarios are modelled on a concept identified by Northern Dynasty’s Pebble Limited Partnership in a request for information submission to the US Army Corps of Engineers (USACE) during the federal permitting process.

The first expansion would expand the Pebble process plant from 180 000 t/d to 250 000 t/d, following the 20-year project life envisioned in the proposed project, with the subsequent mining and processing of an additional 6.3-billion tons of mineralised material.

The second and third expansions would expand the Pebble process plant to 270 000 t/d in production Year 5 and production Year 10, and to 250 000 t/d in Year 21.

All three scenarios process the same 8.6-billion tons of mineralised material over the LoM.

In November 2022, Northern Dynasty updated the PEA for the project to evaluate the impact of the recently announced royalty financing on the project. The 2022 PEA updated the 2021 PEA to examine the impact from the $12-million tranche of the previously completed royalty investment and the potential impact of a $60-million royalty investment if all five tranches are fully committed.

The 2022 PEA highlights that the project remains robust and while the royalty has the potential to be valuable, the impact on the forecasted economics of the project are minimal while strengthening the company’s balance sheet position.

The 2022 PEA also assesses the royalty’s impact on the projected results for the three potential mine expansion scenarios and potential alternative strategies for gold recovery that were also presented in the 2021 PEA, and could form the basis for future permit applications and review.

Potential Job Creation
The project could create 750 to 1 000 direct jobs for Alaskans and 2 000 jobs overall.

Net Present Value/Internal Rate of Return
At forecast long-term metal prices, the project has an after-tax net present value (NPV), at a 7% discount rate, of $2.3-billion and an internal rate of return (IRR) of 15.8%, with a payback of 4.7 years.

At prevailing metal prices, the project has an after-tax NPV, at a 7% discount rate, of $4.8-billion and an IRR of 23.8%.

The expansion studies have an IRR of between 18.2% and 21.5%, and an NPV of between $5.8-billion and $8.5-billion.

Without a royalty, the 2022 PEA calculates an after-tax NPV, at a 7% discount rate, of $2.28-billion and an IRR of 15.7%. Calculating for a 6% silver royalty, the NPV remains virtually unchanged, at $2.45-billion, and the IRR at 15.6%. Working on a 10% gold and 30% silver royalty, the NPV is $2.01-billion and the IRR 15.1%.

Capital Expenditure
Initial capital costs for the proposed project are estimated at $6.05-billion, and do not include the projected costs of any of the expansion scenarios. Additional capital expenditures would be required to facilitate the addition of an on-site gold plant and development of the various expansion scenarios.

Planned Start/End Date
Not stated.

Latest Developments
The state of Alaska has asked the US Supreme Court to vacate a Biden-administration veto blocking Northern Dynasty Minerals' proposed Pebble project, as the state argues that the move violates the land swap deal, in effect from 1976, and the state’s sovereignty to regulate its lands and waters.

The lawsuit has asked the high court to reverse the US Environmental Protection Agency's (EPA’s) Clean Water Act veto. The agency’s January decision determined that the Pebble project would cause large-scale loss and damage to the Bristol Bay watershed, and prohibited the project from dumping mining waste into those waters.

The watershed supports the world’s biggest sockeye salmon fishery and is known for its large mineral resources. It also provides habitat for 29 species of fish, more than 190 birds and dozens of mammals, according to the EPA.

The EPA’s decision illegally blocks development that is “critical to the continued wellbeing of Alaska, which has long relied on its resource-rich lands to fund the state and local governments,” the state has said.

The EPA is reviewing the filing. A representative for Northern Dynasty didn’t immediately respond to a request for comment.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Northern Dynasty Minerals, tel +1 604 684 6365 or email info@northerndynasty.com.
Pebble Limited Partnership, tel  +1 907 339 2600 or email receptionist@pebblepartnership.com.

Edited by Creamer Media Reporter

Comments

 

Showroom

Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.1 0.151s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: