PEA provides ‘strong start’ to Barkerville’s Cariboo gold project
The preliminary economic assessment (PEA) for the Cariboo gold project, in the historic Wells-Barkerville mining camp of British Columbia, provides a solid base-case for the project, which boasts low capital costs and “superb” production expansion potential.
Early this week, Barkerville published a PEA for the 185 000 oz/y Cariboo project, which put forward a net present value of C$402-million, an aftertax internal rate of return of 28% and capital expenditure of C$306-million.
The PEA is based on only 50% of the current mineral resource estimate of Cariboo, president and CEO Chris Lodder pointed out in a statement.
“This is a very strong start to a project that is growing as new resources are being delineated by our ongoing successful exploration at depth and on strike of the present resources and throughout the 2 000 km2 prospective land package.”
The PEA envisions mining up to 4 000 t/d using a long-hole mining approach, focused on extracting large panels with minimum widths of 3.7 m and minimum height of 30 m. The project should produce a high-quality concentrate averaging 20.5 g/t gold at the mine site and continued use of the upgraded Quesnel River mill for final processing.
This, along with optimisation of the mining method, allowed Barkerville to include lower grade resources in the mine plan.
Barkerville’s vision of building a long life, high economic margin, low environmental impact mine in one of Canada's great historic mining camps will now enter the permitting and advanced engineering stage.
This PEA foresees a project that will have a significant economic impact and minimal environmental impact for the Cariboo region of British Columbia, with the potential of generating over C$3.39-billion of gross revenue and contributing about 320 permanent jobs during the production phase, and an additional 120 during the construction phase.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation