Ora Banda pours first gold
PERTH (miningweekly.com) – First gold has been produced at the Davyhurst gold processing plant, in Western Australia.
ASX-listed Ora Banda Mining on Monday reported that the 1.2-million-tonne-a-year Davyhurst plant had been successfully re-commissioned, including the new 8.25 MW gas and diesel-fired power station, upgraded bore fields, process plant chemical storage facilities, upgraded road infrastructure and an upgraded 172-room camp.
MD David Quinlivan said that the first gold pour marked a significant milestone for Ora Banda, as the company transitions from developer to producer.
“We are pleased to reach this important milestone and congratulate all who have been involved in the accomplishment. It has been an impressive team effort to deliver this project into production under the uniquely challenging circumstances of 2020 and 2021. Our focus now remains on the continued ramp-up of activity as we progress towards steady state and the ultimate goal of delivering a long-life and sustainable gold operation.”
Processing operations are currently stable and running at a throughput rate of one-million tonnes a year, and will continue to ramp up. The project is expected to produce some 81 000 oz/y of gold over an initial mine life of five years.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation