https://www.miningweekly.com

Olaroz lithium facility – Stage 2 expansion project, Argentina

1st March 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Olaroz lithium facility – Stage 2 expansion project.

Location
The project is located in Jujuy province, in northern Argentina.

Client
The project is a joint venture between Orocobre and Toyota Tsusho Corporation.

Project Description
The first sale of lithium carbonate from the Olaroz lithium facility started in late April 2015 and volumes have been increasing since then.

The Stage 2 expansion will increase lithium carbonate production capacity by about 25 000 t/y, bringing total Olaroz production capacity to an estimated 42 500 t/y.

The expansion will produce technical-grade lithium carbonate (>99%), part of which will be used as feedstock for the proposed Naraha lithium hydroxide plant to be built in Japan.

During the development of Stage 2, the Stage 1 plant will progressively migrate to 100% battery-grade lithium carbonate production.

Once full production rates have been achieved, the product distribution post Stage 2 is expected to be:

• 17 500 t/y of battery-grade lithium carbonate;

• 9 500 t/y technical-grade lithium carbonate as feedstock for 10 000 t/y battery-grade lithium hydroxide production at the Naraha lithium hydroxide plant; and

• 15 500 t/y of technical-grade lithium carbonate.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Value
The capital expenditure for Stage 2 is expected to be $295-million, including $25-million contingency.

This estimate excludes the crystalliser/evaporator project, which will operate for Stage 1 and Stage 2 on which feasibility studies are currently being undertaken.

The expected cost of this project is about $15-million and will be subject to normal joint venture capital approval processes in due course.

Duration
Commissioning of Stage 2 at Olaroz and the Naraha lithium hydroxide plant are expected to occur during the second half of 2020.

Latest Developments
None stated.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Orocobre, tel +61 7 3871 3985 or email mail@orocobre.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.043 0.717s - 111pq - 2rq
Subscribe Now