Nyanzaga gold project, Tanzania – update
Name of the Project
Nyanzaga gold project.
Location
The Lake Victoria Goldfields region, in north-west Tanzania.
Project Owner/s
Nyanzaga Mining, the direct Tanzanian holding company of the Nyanzaga project, in which OreCorp has a 25% shareholding. The remaining 75% interest in the Nyanzaga project is held by subsidiaries of Acacia Mining. OreCorp and Acacia are parties to an agreement whereby, subject to regulatory conditions, OreCorp will hold (through its subsidiary) 100% of the project.
Project Description
A prefeasibility study (PFS) has confirmed a robust project and has determined that a concurrent openpit and underground mine schedule represent the optimum mining sequence.
The openpit will deliver the base load of mineralised material over the life-of-mine and is expected to deliver about 1.75-million ounces of contained gold over its 12-year mine life – an increase of 25%, or 350 000 oz of gold, on the scoping study assessment.
Underground mining will start in Year 1, from a boxcut outside the openpit, and is expected to produce about 1.16-million ounces of contained gold, including underground development material. The underground deposit will be developed to a depth of 800 m below surface, with the deposit remaining open at depth. Detailed metallurgical testwork in the PFS has confirmed gold recovery of 88% through a conventional four-million-tonne-a-year carbon-in-leach processing plant – an increase of 3% on the scoping study figure.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
Not stated.
Capital Expenditure
Preproduction capital costs are estimated at $287-million, which includes a $33-million contingency. The change in capital from the $248-million in the April 2016 scoping study is largely because of the change in the mine schedule, resulting in an increased prestrip of 7.1-million tonnes, increasing the cost of the prestrip from $14-million to $36-million.
The process plant capital cost has increased by about $11-million, resulting from the reduced grind size (P80 of 75 μm, compared with P80 of 106 μm) and the inclusion of additional processing equipment to improve plant availability and operability. The higher initial capital cost, compared with the scoping study estimate, is offset by the increased average yearly life-of-mine (LoM) production and overall LoM ounces while retaining consistent capital intensity. Consistent with the scoping study, the capital estimate is based on a contractor mining scenario and, therefore, excludes capital for a mining fleet.
Planned Start/End Date
Not stated.
Latest Developments
OreCorp will raise A$56-million through an institutional placement to fund the development of its Nyanzaga gold project.
The company will place 70-million shares at 80c each to domestic and overseas institutional and sophisticated investors. The placement will be conducted under the company’s existing placement capacity.
The funds will enable OreCorp to complete a definitive feasibility study and predevelopment activities at Nyanzaga, and will fund exploration activities at OreCorp’s Western Australian assets and general working capital
Key Contracts and Suppliers
None stated.
Contact Details for Project Information
Acacia Mining GM investor relations and communications Sally Marshak, tel +44 20 7129 7150 or email ir@acaciamining.com.
OreCorp CEO and MD Matthew Yates, tel +61 0 417 953 315.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation