Nimba iron-ore project – Phase 2, Liberia – update

18th June 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Nimba iron-ore project – Phase 2.

Location
Liberia.

Project Owner/s
ArcelorMittal Liberia, a subsidiary of ArcelorMittal.

Project Description
ArcelorMittal has completed a revised detailed feasibility study for the modular construction of a 15-million-tonne concentrator, with aligned mine, concentrate, rail and port capacity.

Phase 2 is considered to be a brownfield project.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
The project will require capital expenditure of $800-million.

Planned Start/End Date
Construction on Phase 2 of the project started in 2013; however, the project was suspended, owing to the onset of Ebola in West Africa, and the subsequent force majeure declaration by the on-site contracting companies. The project is now expected to restart construction in 2021, with first concentrate expected in the fourth quarter of 2023.

Latest Developments
ArcelorMittal plans to restart the expansion of its iron-ore operations in Liberia this year, with first concentrate expected towards the end of 2023.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
ArcelorMittal corporate communications, tel +44 207 543 1128 or email press@arcelormittal.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.044 0.944s - 111pq - 2rq
Subscribe Now