New study gives hope to Sandstone
PERTH (miningweekly.com) – An independent re-optimisation study on the Sandstone gold project, in Western Australia, has proven that the plant could be profitably refurbished using feed from ASX-listed Middle Island’s existing mineral resource.
The study used a range of contemporary gold prices and revised slope parameters, while maintaining the basis of a 2016 prefeasibility study (PFS).
The Two Mile Hill, Shillington and Wirraminna openpit deposits were included in the re-optimisation study, while only the Two Mile Hill and Shillington deposits were considered in the initial PFS, which at the time found that while successful on an operational basis, the economics of the Sandstone project were insufficient to support the capital required to recommission the project.
Middle Island on Friday said that the PFS will now be updated in the current quarter, with a view to re-commission the Sandstone processing plant on a standalone basis.
Mining consultants GR Engineering Services have confirmed that the processing plant could be refurbished within a 16-week timeframe from the start of site work, at a cost of A$10.3-million.
Middle Island told shareholders that discussions have now started on financing the plant refurbishment and the recommissioning, while permits are already in place to start mining once the plant is recommissioned.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation