Name and Location
New Liberty gold project, Liberia.

Client
Aureus Mining.

Project Description
New Liberty will be Liberia’s first commercial gold mine and Aureus’s first mine in its highly prospective 1 470 km2 Liberian licence portfolio.

A definitive feasibility study (DFS) completed on the project in 2013 envisioned an openpit mining operation, extracting ore at a nominal rate of 1.1-million tonnes a year. The openpit will comprise two adjacent and interconnecting pits.

Aureus has continued to conduct further evaluation, including grade-control drilling to produce a better geological understanding of the orebody. Using this information, an optimal new mine plan has been produced.

The plan compensates for the delay and improves the project’s economics. It reduces costs over the life-of-mine (LoM) and generates stronger cash flows, particularly during ramp-up and the first six months of production, resulting in significantly increased free cash flow after debt servicing.

The new mine plan will result in:
• stronger cash generation, particularly in the early stages of the project, for exploration and working capital;
• greater operational flexibility through the creation of two starter pits, providing increased face length and stockpile management, as well as greater confidence that production targets will be met;
• increased run-of-mine (RoM) ore stockpiles, which will provide security for any unforeseen production disruption; and
• reduced mining cash costs, based on more efficient mining, using the layout of the mining infrastructure such as the waste dumps.

The new mine plan involves a revised mining sequence, now running from east to west, which uses two shallower starter pits at Kinjor and Larjor. This provides increased operational flexibility, owing to the increased workable face lengths, and allows for access to areas of high-grade ore earlier in the LoM.

A drainage berm surrounding the openpit, built from waste rock, has also been incorporated into the new mine plan. This not only shortens the haulage distance for waste rock but also lowers the project execution risk during the wet season by safely reducing water ingress into the pit, minimising the pumping required to keep the pit fully operational throughout the wet season.

The plan also incorporates increased efficiencies in the mining fleet and schedule, including ‘hot-seat changeover’ at the start and end of shifts, and temporary haulage ramps to the north of the pit to minimise waste haulage distances. This allows for more waste rock to be removed and for ore to be mined and processed earlier in the mining schedule. The plan also has the incremental benefit of the current low fuel prices, which help to reduce the overall mining costs.

The incorporation of two starter pits, combined with increased mining and trucking efficiencies, has enabled the company to develop a more refined stockpile strategy outlined in the DFS. The increased early tonnage in the new schedule enables Aureus to create a larger stockpile of ore on the RoM pad, allowing higher ore-grade material to be blended and fed to the process plant earlier than estimated in the original schedule. This also safeguards Aureus from any potential problems in the pit by having more ore material available for processing. The stockpile-blending strategy facilitates a consistent grade of ore to be supplied to the process plant. Additional oxide material will be blended with sulphide ore during dry seasons, improving plant throughput by an estimated 15%.

The revised production profile is more appropriately aligned to the current gold price environment. The basis of the new plan is that 10% more ore material will be mined and 35% more gold will be produced in 2015, compared with the figures of the delayed DFS mine plan. These revisions more than adequately compensate for the delay in processing operations caused by the Ebola outbreak.

The New Liberty gold deposit has a total mineral reserve estimate of 923 716 oz of gold grading 3.4 g/t. It comprises 704 600 t grading 4.4 g/t in the proven mineral reserve category, and 7.79-million tonnes grading 3.3 g/t in the probable mineral reserve category.

Net Present Value/Internal Rate of Return
Pretax net present value from production, at a 5% discount rate, is estimated at $365-million in the new mine plan.

Value
Total cost associated with implementing the new mine plan, estimated at $15-million, pertains to the increased prestrip mining activities having occurred during the delay period. Aureus has financed this new mine plan through its existing debt finance facilities. The remaining existing cash resources will finance the completion of the construction of New Liberty and fund general working capital.

Duration
Aureus declared commercial production at the mine in March 2016.

Latest Developments
The New Liberty mine has been temporarily suspended, owing to problems with the detoxification circuit in the process plant.

The detoxification circuit has not been operating to original design specifications, resulting in higher concentrations of weak acid dissociated cyanide in the process effluent.  

The plant has been operating with process water in a closed circuit, with zero discharge from the tailings storage facility (TSF); however, recent heavy rainfall has inadvertently resulted in a small overflow of effluent from the TSF into the wetlands area within the mining lease area. 

Aureus has reported that it is conducting remediation work to rectify the issues in the detoxification circuit and to manage future water discharge from the TSF.

According to investigations conducted by Aureus, to date no adverse impact on any human settlement has been found, as the discharge took place within the mining lease and about 5 km from the nearest settlement. 

However, further investigations are in progress and, as a result of this leakage, Aureus has decided to suspend processing operations.

SRK Consulting staff are on site to assist Aureus’s engineering staff with the evaluation of the adjustments to be made to the waste neutralisation section of the detoxification circuit and the management of water discharge from the TSF for processing operations to restart.

Aureus and its subsidiary Bea Mountain Mining Corp are coordinating work with the Environmental Protection Agency (EPA) of Liberia and the Ministry of Lands, Mines and Energy (MLME) and local downstream communities to mitigate against any environmental risks.

The EPA is reviewing and approving the proposed remediation work required to rectify the detoxification circuit and to manage future water discharge from the TSF.  

Approval from the EPA and MLME will be required before gold processing operations can resume.

During the suspension of processing operations, Aureus is implementing a mill reline and undertaking other scheduled preventive engineering maintenance and repairs, as well as modifications to the detoxification circuit.  

Mining operations are continuing, with ore stockpiles to be built up.

Key Contracts and Suppliers
DRA (engineering, procurement and construction management contractors); Australian Mining Consultants (National Instrument 43-101 resource classification, and openpit and mining optimisation studies); Digby Wells Associates (environmental and social advisers) and MonuRent (mining fleet rental and maintenance partner).

 

On Budget and on Time?
Despite Aureus’s maintaining construction activities throughout the peak of the Ebola crisis, in Liberia, first gold pour was delayed from March 2015 to the end of May 2015, as a result of logistical and other difficulties beyond the company’s control.

Owing to this delay, the DFS mine plan of 2013 failed to provide sufficient operational flexibility during the production phase, and rather increased execution risk amid potential operational outages. This was primarily because the DFS mine plan was based on a single starter pit, minimising operational face lengths and not allowing for enough gold-bearing ore to accumulate on the stockpile to feed the plant during a power outage.

 

Contact Details for Project Information
Aureus Mining CEO and president David Reading or CFO Paul Thomson, tel +44 207 1017 690.
 
 
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rio-Carb
Rio-Carb

Rio Carb is an OEM (Original Equipment Manufacturer) of R-C700 Chromium Carbide (CrC) alloy clad wear plates and pipes used for heavy materials...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.042 0.803s - 111pq - 2rq
Subscribe Now