New Acland Stage 3 coal mine expansion project, Australia

23rd February 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
New Acland Stage 3 coal mine expansion project.

Location
Queensland, Australia.

Client
New Acland Coal (NAC), a subsidiary of the New Hope Group.

Project Description
NAC currently operates the existing New Acland coal mine as a 4.8-million-tonne-a-year opencut coal mine on mining lease (ML) 50170 and ML 50216. The mine has reserves that will allow for current operations to continue until about 2017.

The project will expand the mine’s yearly output from 4.8-million tonnes to 7.5-million tonnes and will extend the operation’s life beyond the current end-date of 2017/18.

The revised coal project proposes to develop Stage 3 of the New Acland mine, which involves the extension of the mine’s operating life to about 2029, including the progressive development of two new resource areas within the area covered by Mining Development Licence 244, also covered by ML Application 50232.

The two resource areas will be developed sequentially and combined with the current operations to supply up to 7.5-million tonnes a year of saleable product coal for the export and domestic markets until about 2029.

Key features of the project include:
• developing parts of the Manning Vale and Willeroo resource areas;
• upgrading the existing coal handling and preparation plant and supporting infrastructure;
• constructing a new coal load-out facility on the mining lease and an estimated 8 km rail spur, as a result of the relocation of the existing Jondaryan coal load-out facility; and
• roadworks and constructing water management structures, as well as relocating and potentially upgrading the power supply to the revised project.

The Acland town area, including Tom Doherty park, the War Memorial and the Acland No 2 colliery and utility services, will be maintained over the life of the revised project.

The closest point of potential mining operations will be at least 10 km away from Oakey, compared with the 7 km previously proposed.

The land disturbed for mining activities will be reduced by more than half, compared with the original Stage 3 proposal.

Veneering to coat all transported coal leaving the mine by train as a measure to reduce the potential for coal dust coming from trains will continue.

Lagoon Creek will not be diverted as previously proposed. Operations will continue to be self-sufficient for water, with water continuing to be bought from Toowoomba’s Wetalla wastewater reclamation facility. Only about 20% of the Wetalla water is bought by NAC.

Production levels from the New Acland mine will be reduced by at least 25% to 7.5-million tonnes a year, from the originally proposed ten-million tonnes a year.

Potential Job Creation
The expanded operation will result in employment for 260 people at the mine, and ongoing employment of up to 435 jobs, and, indirectly, 2 300 jobs.

Net Present Value/Internal Rate of Return
Not stated.

Value
A$900-million.

Duration
About 2.5 years will be required to complete the design, build and other related activities to facilitate the revised project.

Latest Developments
New Hope’s plans to expand its New Acland mine have been dealt a blow, as the Department of Environment and Science (DES) has refused its application for an amended environmental authority (EA).

The DES has not provided much information about its decision, as it may be subject to legal action, but said that its refusal is in line with the recommendation of the Land Court, which was handed down in May last year.

Disappointed with the outcome of the DES process, New Hope is considering its options.

New Hope has previously called for a judicial review of the Land Court’s decision, which has raised concerns about the impact of the proposed expansion on groundwater in the region, recommending that the mining lease and EA not be granted.

Queensland Resources Council CEO Ian Macfarlane has said that the decision will hurt regional job prospects, noting the importance of the mine to the Darling Downs.

Key Contracts and Suppliers
Not stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
New Acland Coal, tel +61 7 3418 0500, fax +61 7 3418 0355 or email aclandinfo@newhopegroup.com.au.
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.079 0.847s - 111pq - 2rq
Subscribe Now