Mt Garnet study progresses to definitive feasibility stage

1st October 2013

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – A prefeasibility study (PFS) at ASX-listed Consolidated Tin Mines' Mount Garnet project, in Queensland, has demonstrated robust economics, supporting the progression to a definitive feasibility study (DFS).

The PFS found that with a capital spend of A$76-million, the Mount Garnet project could be an one-million-tonne-a-year opencut operation, producing 2 944 t/y of tin in concentrate.

The project, which was expected to have a minimum mine life of nine years, would generate an yearly revenue of around A$127.4-million, with production costs estimated at A$91.94/t.

The Mount Garnet project was estimated to have a net present value of A$184.1-million before tax, and an internal rate of return of 111% after tax.

“The study demonstrates the economics of a robust and significant tin project. Unlike other projects, Mount Garnet boasts existing infrastructure and near-surface ore, which are the drivers of low capital and operating costs,” said Consolidated Tin chairperson and MD Ralph de Lacey.

“The PFS has confirmed that we have the opportunity to develop a substantial and profitable tin mining project.”

De Lacey noted that another important outcome of the PFS was the identification of a number of opportunities to improve the financial aspect of the project with further design optimisation of the mining and processing stages, adding that these opportunities would be realised through the DFS process.

“The board has approved the initiation of the definitive feasibility study for the Mount Garnet tin project, starting with the Gillian prospect, with further evaluation work to follow at Pinnacles and later at Windemere. It is anticipated that Gillian will provide the mill feed for the first three years of mining,” he added.

De Lacey also noted that discussions were well advanced with Consolidated Tin’s major shareholder, Snow Peak, to finalise a binding agreement to ensure that the full asset value was realised, and with the aim of achieving first tin production by the end of 2014.

Edited by Mariaan Webb
Creamer Media Contract Publishing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.047 1s - 128pq - 2rq
Subscribe Now