Mount Mackenzie gold project, Australia

8th May 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Mount Mackenzie gold project.

Location
Bowen basin, in Queensland, Australia.

Project Owner/s
Resources & Energy Group.

Project Description
A scoping study has highlighted a strong case for the development of an opencut gold mining operation and the processing of three gold resources – North Knoll, South West Slopes and Lode 355 – within the project area, with scope for growth in the resource by targeting the extent of the untested primary ore.

The scoping study investigated a range of production and processing options and has identified a 300 000 t/y opencut development, with an on-site gold plant as the most appropriate case for the progression of the project to feasibility study.

The processing plant is proposed to be a low-cost modular crushing, grinding and carbon-in-leach circuit.

The scoping study incorporates indicated and inferred resources of 2.37-million tonnes grading 1.31 g/t gold for 100 000 oz of contained gold and 2.37-million tonnes grading 8.2 g/t silver for 624 000 oz of contained silver.

Gold and silver production is estimated at 43 200 oz and 242 400 oz respectively over a 43-month period.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Project capital expenditure is estimated at $13-million.

Planned Start/End Date
Not stated.

Latest Developments
Resources & Energy Group is reviewing its Mt Mackenzie gold/silver project to incorporate a higher gold price.

The company has restarted the scoping study using a gold price of A$2 600/oz, which has resulted in an increase of the projected free cash flow from A$30.5-million to A$54.6-million, while operating cash flow is projected to be A$67.6-million.

The company has now initiated a revised mineral resource estimate, pit optimisation and life-of-mine scheduling for a 500 000 t/y development option using the revised gold price.

This review will be released shortly, the company has said.

Key Contracts and Suppliers
None stated.

Contact Details for Project Information
Resources & Energy Group, tel +612 92278900 or email communications@rezgroup.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.058 0.717s - 111pq - 2rq
Subscribe Now