Name of the Project
Monty copper/gold project.

Location
Western Australia.

Client
The Monty project is part of the Springfield Unincorporated Joint Venture, which comprises participating interests of Sandfire (as manager with a 70% interest) and Talisman Mining (30%).

Sandfire has agreed to acquire Talisman’s 30% share of Monty ore under an ore sale and purchase agreement, with all the ore from the Monty project to be processed at the De Grussa processing plant.

Project Description
A feasibility study on the Monty project has confirmed its suitability to be developed as a satellite source of high-grade ore feed for the existing DeGrussa operation.

The project has a maiden ore reserve of 920 000 t grading 8.7% copper and 1.4 g/t gold for 80 000 t of contained copper and 42 000 oz of contained gold on a 100% basis.

The mine plan incorporates the mining of the lower zone, which is the higher-grade portion of the ore reserve. 

The upper zone, while marginally economic, will be subject to further technical and economic assessment in due course. 

The feasibility study envisages the development of an underground mine, using long-hole open stoping.

The project includes the development of more than 10 km of lateral development and 500 m of vertical development. 

As with DeGrussa, further drilling of the Monty orebody will be completed from access points along the decline to assist with grade control, mine development planning and further metallurgical testwork.

Monty will produce an estimated 70 000 t of copper and 21 000 oz of gold, as well as 288 000 oz of silver, over a three-year period, following one year of access development.

Jobs to Be Created
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Value
Project value is estimated at $90-million.

Duration
Development of the boxcut is expected to start in the second quarter of the 2018 financial year. 

Ore production is expected to start in the second quarter of the 2019 financial year, with first stoping to follow soon thereafter.

Latest Developments
Sandfire Resources has awarded an A$8.2-million civils and earthworks contract for the Monty mine to the Yagahong Alliance, a joint venture between Geraldton-based contractor Central Earthmoving and the Yugunga-Nya People, the traditional owners of the project areas.
The civils and earthmoving contract encompasses the development of a 14-km-long haul road from the Monty operation to the Degrussa copper/gold mine, local access roads, stockpile and laydown area pads, the cutting of a boxcut for underground access and additional infrastructure works and drainage.
Site work is expected to start immediately.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Sandfire Resources, tel +61 8 6430 3800, fax +61 8 8430 3849 or email admin@sandfire.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.044 0.764s - 111pq - 2rq
Subscribe Now