Montepuez graphite project, Mozambique
Name of the Project
Montepuez graphite project.
Location
Mozambique.
Client
Battery Minerals.
Project Description
A value engineering study (VES) has determined that the restructure of the Montepuez graphite project will result in the generation of outstanding financial returns.
The aim of the VES was to:
• significantly improve financial returns highlighted in the February definitive feasibility study (DFS) by optimising the processing plant through modularisation;
• refine the mine plan to produce a higher head grade;
• adopt an owner-operator mining and accommodation model to remove the use of contractors; and
• reduce the size of the initial tailings dam and water supply facility.
Concentrate recoveries were also increased through a series of successful metallurgical and processing testwork.
Under the VES, the Montepuez process plant will initially process run-of-mine ore at an average of 500 000 t/y at 12% total graphitic carbon (TGC) to produce 45 000 t/y to 50 000 t/y of dry graphite concentrate with an average grade of 96.7% TGC.
Compared with the February DFS, the VES has also reduced the expected life-of-mine from 30 years to 10 years, with concentrate production decreasing from 100 000 t/y to between 45 000 t/y and 50 000 t/y.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 10% discount rate, of $146-million and an internal rate of return of 36.2%.
Payback has been reduced from 4.75 years in the DFS to two years in the VES.
Value
Total capital expenditure in the VES is estimated at $42.33-million, compared with $126-million in the February definitive feasibility study.
Duration
Construction is expected to start in the second quarter of 2018, with steady-state production expected to be reached in the final quarter of 2019.
Latest Developments
None stated.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Battery Minerals, tel +61 8 9322 7600, fax +61 8 9322 7602 or email info@batteryminerals.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation