Montanore silver/copper project, US
Name and Location
Montanore silver/copper project, Montana, US.
Client
Mines Management Incorporated.
Project Description
The project envisages an underground mining operation using conventional grinding and flotation processes. The deposit will be bulk-mined 350 days a year and use an inclined room-and-pillar mining method, producing at a nominal rate of 12 500 t/d, although the mine is being permitted for a throughput of up to 20 000 t/d.
Over the 15-year mine life, an estimated 59-million tons of process feed will be treated at average grades of 1.88 oz/t of silver and 0.72% of copper, yielding 96-million ounces of silver and 767-million pounds of copper.
Under the current mine plan, 40-ft-wide topslices will be mined on strike below the hanging wall contact. Connection drifts between adjacent top cuts will be mined following the hanging wall contact at a gradient of 15%, forming obliquely angled permanent stope pillars. Mineralisation below the topslice will be mined using a longhole bench.
Mining at Montanore is planned to be highly mechanised, using large high-tech mining equipment, including modern load-haul-dump units and trucks and computer-controlled drilling jumbos.
Net Present Value/Internal Rate of Return
The project has a net present value of $485.6-million and an internal rate of return of 17.4%.
Value
Total project costs are estimated at $552.32-million in the 2011 technical report.
Duration
Not stated.
Latest Developments
Mines Management has received records of decision approving development of the Montanore mine from the US Forest Service and the Montana Department of Environmental Quality.
The agencies’ decisions signal the approval of project development.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Mines Management, tel +1 509 838 6050.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation