Molyhil tungsten project, Australia
Name and Location
Molyhil tungsten project, Northern Territory, Australia.
Client
Thor Mining.
Project Description
The upgraded feasibility study on Molyhil envisages mining using conventional opencut, as well as contract drill and blast methods, followed by owner-operated excavation and haulage.
The resource estimate extends below the level of the opencut ore reserve used in this study, allowing for the project life to be extended, either by deepening the openpit or by using underground mining methods depending upon subsequent costs and metal prices.
Mineral processing will involve:
• two-stage crushing to −55 mm;
• X-ray ore sorting at −55 mm to +25 mm and −25 mm to +10mm;
• tertiary crushing;
• two-stage grinding using a rod mill, followed by a ball mill;
• a three-stage flotation circuit – molybdenum, sulphide and scheelite flotation; and
• concentrate dressing.
The revised process flowsheet involves replacing the previous scheelite gravity recovery method with flotation, which has achieved substantial improvements in economic recovery.
It has also been successful in reducing the levels of some deleterious elements in final concentrate, compared with the original circuit. The scheelite concentrate dressing process, which follows the flotation step, has been tested, but is not yet optimised. It is expected that this optimisation process will be completed during the detailed design phase.
Net Present Value/Internal Rate of Return
The upgraded feasibility study estimates an all equity net present value of A$67-million with an internal rate of return of 44%, after taxation and royalty payments, with a payback period of 18 months after payment of royalties and taxation.
Value
Capital expenditure of A$70-million.
Duration
Not stated.
Latest Developments
The next steps for the Molyhil project involve securing the balance of concentrate sales (offtake) agreements and finance for project development, after which detailed engineering studies, along with the completion of the mine management plan and on-site civil works, will start in preparation for mine and process plant construction, as well as development.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Thor Mining, tel +61 8 7324 1935, fax +61 8 8351 5169 or email corporate@thormining.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation