Mofe Creek iron-ore project, Liberia.

Client
Tawana Resources.

Project Description
A scoping study on the Mofe Creek project has delivered excellent technical and financial results, along with project design and development simplicity.

A scoping study has found that the project will have an initial mine life of 14 years.

The study has also identified an opportunity to fast-track the initial one-million-tonne-a-year to 2.5-million-tonne-a-year production scenario using existing infrastructure in Liberia, including a sealed road from the Gofolo mine to the Port of Monrovia and an existing deep-water port at Freeport-Monrovia. As the project expands, the Freeport capacity will be exceeded and alternative transshipment or shiploading facilities will be required.

The project development plan envisages a staged production ramp-up starting at one-million tonnes a year (Stage 1A) and then increasing production to 2.5-million tonnes a year (Stage 1B).

Net Present Value/Internal Rate of Return
The project has a net present value at 8% discounted cash flow, after royalties at 4.5% of $435-million. The pretax internal rate of return is estimated at 55.8%.

Value
The initial capital expenditure (capex) required for first production is estimated at $52.9-million, which is inclusive of a 20% contingency on capex.

The total capital cost required to achieve and sustain 2.5-million tonnes a year, including an independent haul road and a transshipment facility at the coast of Liberia, is estimated at $280-million.

This is inclusive of a 20% contingency on capex.

Duration
The timeline to initial production is 15 months from the approval of a mining licence.

Latest Developments
Tawana plans to immediately start a prefeasibility study on the project.

The will also advance discussions with potential strategic partners, offtakers, debt providers and financiers to fast-track the development of the project.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Tawana Resources, tel +61 8 9287 4333 or fax +61 8 9389 3199.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

CSIR International Convention Centre (CSIR ICC)
CSIR International Convention Centre (CSIR ICC)

CSIR International Convention Centre (CSIR ICC) - the leading conference and events venue in Pretoria/Tshwane.

VISIT SHOWROOM 
Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.07 0.729s - 111pq - 2rq
Subscribe Now