Merlin diamond project, Australia

Merlin diamond project, Australia

25th February 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Merlin diamond project.

Location
Northern Territory of Australia.

Project Owner/s
Lucapa Diamond Company.

Project Description
A scoping study has shown robust economics for a long-life mine development using conventional openpit and vertical pit mining techniques.

The project will have a processing capacity of about 1.2-million tonnes a year, treating 14-million tonnes over the envisaged 14-year life-of-mine (LoM), with average diamond production estimated at 153 000 ct/y.

The project has a production target of 2.1-million carats over the estimated LoM.

Production over the LoM will be predominantly sourced from indicated and inferred resources, with an estimated 71% from indicated resources and 29% from inferred resources.

The project has total mineral resources of 27.8-million tonnes for 16 carats per hundred tonnes.

Initially, each of the project’s eight kimberlite pipes will be mined using conventional openpit mining.

When the openpit has been completed to the planned depth, vertical pit mining will be imple­mented to deepen the mine below the base of the openpit.

There is potential for viable underground mining beneath the vertical pit mine on certain pipes; however, this has not been included in the cur­rent scoping study.

Lucapa is undertaking a separate scoping study to evaluate a potential underground development.

Potential Job Creation
The mine will require a workforce of about
200 people.

Net Present Value/Internal Rate of Return
The project has an pretax net present value, at a 7% discount rate, of A$343-million and internal rate of return of 59%, with payback expected by the second year of production.

Capital Expenditure
The project will require an initial capital invest­ment of A$96-million, including waste prestrip of about A$18-million.

Planned Start/End Date
The project is expected to have a two-year devel­opment timeline, owing to the advanced stage of the project and existing infrastructure.

Latest Developments
Lucapa is progressing with the feasibility study, with the results expected in mid-2022.

Key Contracts, Suppliers and Consultants
AMC Consultants (mining study).

Contact Details for Project Information
Lucapa Diamond Company, tel +61 8 9381 5995.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Lion Alcoblow ® - High speed breathalyser

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.267 0.321s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: