Medupi Unit 5 synchronised to South African grid

Medupi team celebrates Unit 5 milestone (from left to right): Deputy Project Director: Sifiso Mazibuko, Power Station Manager: Johan Prinsloo, Project Director: Phillip Dukashe.

8th September 2016

By: Terence Creamer

Creamer Media Editor

  

Font size: - +

Public Enterprises Minister Lynne Brown confirmed on Thursday that the second 800 MW unit at the Medupi coal-fired power station project, in Limpopo, had been synchronised to the grid.

She said in a statement that Unit 5 – one of six being built as part of the 4 800 MW project – would become commercially operational by March 2018. The first unit, or Unit 6, began feeding power into the grid in March 2015 and entered commercial operation on August 23.

Medupi is being built in reverse order in terms of Eskom’s right-to-left nomenclature when viewing its coal-fired power stations from the perspective of the units in front of the stacks. The decision to reverse the order at Medupi was based on the discovery of a rock conglomeration on the southern side of the site, which made it more cost effective to build from left to right.

The project has been afflicted by technical and labour difficulties and is running years behind schedule and well over its initial budget.

In July, Eskom officially updated its cost-to-completion estimates for both Medupi and Kusile – the latter 4 800 MW project is being built in the Mpumalanga province.

The State-owned utility reported that Medupi was now expected to cost R145-billion, rather than the earlier revised estimate of R105-billion, while Kusile was expected to cost R161-billion, not R118-billion. Neither estimate included interest during construction, however.

The entire six-unit Medupi project is expected to be completed in 2020, while Kusile is expected to be in full production only in 2022, with the first unit, Unit 1, expected to begin producing commercially in the second half of 2018. However, synchronisation of Kusile Unit 1 is expected well before that date.

Synchronisation, Eskom explains, is when the generator in the unit is connected into the power grid so that it is aligned with all other generators on the national grid. It then starts to generate and deliver electricity into the grid over several months.

Brown congratulated Eskom for the synchronisation milestone, indicating that it was part of a broader build-programme acceleration being driven by the utility's new leadership.

“This year we have seen the Ingula station’s units 3 and 4 becoming commercially operational, while Medupi’s Unit 6 led the way in the second half of 2015. Over the past 18 months, we have seen 1 800 MW being added to the grid and the new build programme will add 8 600 MW of new capacity by 2020/21,” the Minister enthused.

“There is a new sense of urgency and a drive to succeed at Eskom,” Brown added, singling out CEO Brian Molefe and chairperson Dr Ben Ngubane for specific praise.

Molefe said the Medupi Unit 5 milestone further strengthened the position that "load-shedding is becoming a thing of the past".

Once completed, Medupi will be the fourth largest coal-fired power plant, and the largest dry-cooled power station in the world. Dry-cooling systems use air instead of water to cool the steam exiting a turbine.

The power plant also incorporates super critical technology, which is able to operate at higher temperatures than Eskom’s earlier generation of boilers and turbines.

Edited by Creamer Media Reporter

Comments

Showroom

John Deere (Pty) Ltd
John Deere (Pty) Ltd

In 1958 John Deere Construction made its first introduction to the industry with their model 64 bulldozer.

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.122 0.162s - 106pq - 2rq
Subscribe Now