PERTH (miningweekly.com) – Gold production has started at the Matilda gold project, in Western Australia, with ASX-listed Blackham Resources expected to pour its first gold in the next few days.

Blackham noted that during the September quarter, some 1.57-million cubic metres of material were mined, with mining focused on the removal of overburden to open up ore sources.

Underground mining for the quarter also focused on lateral development around the old Golden Age stopes. There are currently three jumbos on site focused on development and rehabilitation activities.

Mining from the openpits, underground and existing stockpiles has resulted in gold stockpiles of some 172 000 t, grading 1.4 g/t gold for 7 900 oz available for milling, which accounted for a full month of production.

Blackham noted that with ore milling now having started, gold in circuit was accumulating and first gold pour was expected within days.

The expanded Matilda gold project includes Joint Ore Reserves Committee-compliant measured, indicated and inferred resources of 48-million tons at 3.3 g/t for 5.1-million ounces within an 860 km2 exploration tenement package and has historically produced more than 4.3-million ounces.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.056 1.019s - 110pq - 2rq
Subscribe Now