Mana gold project, Burkina Faso
Name and location
Mana gold project, Burkina Faso.
Project description
The Mana gold project has proven and probable reserves of 10,6-million tons, grading 2,92 g/t of gold, including the Nyafe and Wona deposits, containing 997 400 oz of gold.
The project has an estimated eight-year mine life producing gold at an average rate of 125 000 oz/y for the first three years, and 90 000 oz/y for the last five years of mine life. Based on an average recovery rate of 84% the carbon-in-leach (CIL) plant will produce a total of 840 000 oz of gold.
Value
The capital cost of the project is estimated at $58-million, with an additional $12-million for a mining fleet.
Duration
The commissioning of the project is expected at the end of 2007.
Breakdown of main contracts
Not stated.
Client
Semafo.
Latest developments
The principal road construction at the project has been completed. The foundations for the plant are 95% complete. Structural steel for the plant is on site and the erection process is under way. Power generating equipment is on site and is currently being installed.
The stripping of the Won pit is well advanced. A total of 800 000 t of material has been removed and partly used for the construction of the water and tailings dams. The water dam is nearing completion and has begun accumulating water from rainfall. The tailings dam construction is progressing to plan.
Two water tanks and two of the six CIL tanks have been installed, with completion scheduled for July.
The crushing circuit is currently being delivered on-site. The apron feeder is scheduled for delivery in August, as is the elution package and regeneration kiln.
The 2 000-t/d ball mill is scheduled for delivery in September, while the 4 000-t/d ball mill is scheduled for delivery in December. Stripping of the Nave pit was scheduled to start in July.
Participants
Geneva (engineering, procurement and construction management).
Construction materials
Not stated.
On budget and on time?
Work is progressing on schedule.
Contact details for project information
Semafo, tel +1 514 744 4408,
fax +1 514 744 2291 or email info@semafo.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation