Makhado Lite project, South Africa
Name of the Project
Makhado Lite project.
Location
Limpopo, South Africa.
Client
Baobab Mining & Exploration, a subsidiary of Coal of Africa Limited (CoAL).
Project Description
The original Makhado project development plan included a 26-month construction phase followed by a four-month ramp-up to achieve a production rate of 5.5-million tonnes a year, with a capital requirement of $281-million.
While CoAL has progressed regulatory matters on the coal project, it has reviewed its development plan and reassessed its strategy, resulting in an amended plan requiring reduced capital expenditure, a shorter construction period and earlier-than-planned production.
The Makhado Lite project will produce about 1.7-million tonnes a year of saleable coal, comprising 700 000 t/y to 800 000 t/y of hard coking coal, compared with 2.3-million tonnes a year in the original project plan. Thermal coal production has been revised from 3.2-million tonnes to between 900 000 t/y and one-million tonnes a year. In the original Makhado project plan, about 12.6-million tonnes a year of run-of-mine production was estimated, compared with four-million tonnes in the new development plan.
The life-of-mine plan has been extended from 16 years to 29 years.
CoAL expects that a substantial portion of the hard coking coal produced will be sold locally, with the balance sold on international markets.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The net present value of the project has decreased from an estimated $697-million, at an 8% discount rate, to between $135-million and $260-million at a 10% discount rate.
The internal rate of return has increased from 30.1% to between 30% and 50%.
Value
The original Makhado project had an estimated capital expenditure of $406-million. Under the revised development plan, the project is expected to cost between $75-million and $85-million, and allows for the future expansion of mining and production.
Duration
The original Makhado project had a construction period of 26 months. The revised strategy expects that the Makhado Lite project to be built in 12 months.
Latest Developments
None stated.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
CoAL, tel +27 10 003 8000, fax +27 11 388 8333 or email adminza@coalofafrica.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation