Name of the Project
Makhado hard coking and thermal coal project.

Location
Limpopo, South Africa.

Project Owner/s
Baobab Mining & Exploration, the owner of the mining right for the Makhado hard coking and thermal coal project (Makhado project), is majority-owned by MC Mining (69%), formerly Coal of Africa Limited.

The Industrial Development Corporation owns 5% of Baobab’s shares; 20% is held by a community trust, with seven local communities situated in the project’s vicinity being the beneficiaries. The remaining 6% is held by a black industrialist.

Project Description
Makhado is classified as an evaluation asset and has not historically been mined.

The project will be completed in two phases.

Phase 1 will start with the development of Makhado’s west pit, producing three-million tonnes a year run-of-mine (RoM) coal. The coal will be mined by an independent mining contractor using truck-and-shovel, modified terrace mining methods.

RoM coal will be partially beneficiated before being dispatched to MC Mining’s Limpopo Coal Company subsidiary’s modified Vele colliery for processing. About two-million tonnes a year of RoM coal (ex-discard) will be trucked to Vele for processing at the colliery’s enhanced plant. Plant modifications include a new fines circuit comprising a reflux classifier in series with the existing spiral plant, a low-density secondary wash plant and a froth flotation plant to capture the ultrafine coal.

At steady state, the operation will produce 1.1-million tonnes of saleable coal – 540 000 t/y of hard coking coal and 570 000 t/y of 5 500 kcal thermal coal.

The saleable coal will be trucked to the Musina siding for railing to domestic and/or export clients.

Phase 1 is a critical step in the development of Phase 2 of the Makhado project.

Phase 2 involves the implementation of the Makhado Lite plan, which will produce about 1.7-million tonnes a year of saleable coal comprising 700 000 t/y to 800 000 t/y of hard coking coal and between 900 000 t/y and one-million tonnes a year of thermal coal. The project involves the development and mining of the east and west pits, the Makhado processing plant and related infrastructure.

The entire Makhado project has a minimum life-of-mine of 46 years.

Potential Job Creation
Phase 1 mining and processing will be outsourced to experienced third parties that have previously operated in South Africa, and is expected to create about 650 permanent employment opportunities.

Net Present Value/Internal Rate of Return
Phase 1 has an estimated internal rate of return of more than 45%, with a payback of 2.5 years.

Capital Expenditure
Phase 1 will cost about R700-million.

Planned Start/End Date
Construction of Phase 1 is expected to start in 2020 and is expected to take nine months, with first coal-sales expected in the first half of 2021.

Phase 2 will be implemented in about 2022.

Latest Developments
MC Mining expects the process to secure the balance of funding required to start the development of Phase 1 of Makhado will be completed in the second or third quarter of this calendar year, with construction to start shortly thereafter.

According to the company, Phase 1 is a critical step in the development of Phase 2 of the project, which also has significant positive economics. The company has already secured offtake agreements for about 50% of the estimated 800 000 t/y of hard coking coal to be produced in Phase 2.

Key Contracts and Suppliers
Minxcon (competent person’s report).

Proposals for full mining services have been sourced from various contract mining companies, with turnkey processing plant construction and operating quotes obtained from potential service providers.

On Budget and on Time?
Not stated.

Contact Details for Project Information
MC Mining, tel +27 10 003 8000, fax +27 11 388 8333 or email adminza@mcmining.co.za.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

ZF Aftermarket
ZF Aftermarket

ZF Aftermarket is the after-sales division of the world-renowned German ZF group, a global leader in mobility technology.

VISIT SHOWROOM 
Vikela Aluvin (Pty) Ltd
Vikela Aluvin (Pty) Ltd

Complete range of security sealing solutions including security seals bags and labels.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.042 0.216s - 111pq - 2rq
Subscribe Now