Makabingui gold project, Senegal

1st August 2014

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Makabingui gold project, Senegal.

Client
Bassari Resources.

Project Description
The Makabingui project currently hosts a mineral resource that comprises 11.9-million tonnes averaging 2.6 g/t gold for a contained one-million ounces of gold, classified as indicated and inferred resources. The initial mining phase focuses on the indicated component of the resource based on openpit mining, with conventional gravity and carbon-in-leach (CIL) processing circuits.

The feasibility study completed on the project is based on a 300 000 t/y hard-rock operation, initially from four high-grade openpits delivering 50 000 oz/y over a 3.4-year mine life. Processing will be undertaken in two stages.

Stage 1 will be a circuit to maximise gravity recoverable gold, with Stage 2 being a conventional CIL circuit. The plant will be operated 24/7, with a design availability of 90% and a processing treatment rate of 38 t/h.

Additionally, there is exploration and mine-life upside within the Makabingui one-million-ounce resource and the prospective area to the south.

Net Present Value/Internal Rate of Return
The project has an estimated net present value of $63-million and an internal rate of return of 404%, with payback from the start of production estimated at 12 months.

Value
The project is estimated at $12.1-million.

Duration
An indicative development timeframe to first gold production is eight months, with the critical path being the processing plant construction.

Latest Developments
Bassari is considering several options to fund the development of the project.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Bassari Resources, tel +613 9614 0600, fax +613 9614 0550 or email admin@bassari.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.045 0.704s - 111pq - 2rq
Subscribe Now