Longonjo neodymium/praseodymium project, Angola – update

LOCATION MAP OF THE LONGONJO MINING OPERATION

Location map of the Longonjo neodymium/praseodymium project

Photo by Pensana

8th March 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Longonjo neodymium/praseodymium project.

Location
Huambo, Angola – 4 km from a modern rail line leading directly into the Port of Lobito in the Atlantic Ocean.

Project Owner/s
Pensana Rare Earths holds an 84% interest in Longonjo through its 84% holding in Angola-registered company Ozango Minerais, which, in turn, owns 100% of the mining licence.

The Angolan government holds a 10% interest and the company’s Angolan partners the remaining 6%.

Project Description
Longonjo is one of the biggest rare earths deposits in the world, with an initial 20-year mine life.

The project has total proven and probable reserves of 30.1-million tonnes grading 0.55% neodymium/praseodymium oxide for 166 000 t neodymium/praseodymium and total rare-earth oxides (TREOs) of 767 000 t.

The mine execution plan is based on a staged development of the mine and processing facilities.

At full production, once the phased development is complete, the Longonjo mine will target production of up to 38 000 t/y of mixed rare-earth double sulphate or mixed rare-earth carbonate (MREC) containing 14 000 t of TREOs and up to 4 400 t of neodymium/praseodymium oxides. This equates to about 5% of the worldwide production of neodymium/praseodymium oxides a year for downstream processing or to be sold on the international market.

Initial feedstock will be shipped as a clean, high-purity mixed rare earth sulphate to Pensana’s Saltend rare earth oxide separation facility, in the UK.

Potential Job Creation
The mine will employ about 650 people during construction and will create 420 permanent, high-value jobs.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
£217-million for the fully permitted mine and processing facilities.

Planned Start/End Date
Longonjo is expected to produce 20 000 t of MREC starting in 2026 and 40 000 t of MREC from 2029 onwards following the planned expansion.

Latest Developments
Pensana has reported that preparatory works are advancing smoothly at the Longonjo project, with the main construction expected to start in May 2024 and cold commissioning to follow in August 2025.

The detailed design and procurement documentation for other main long-lead time and critical path items, such as the thickeners and flotation columns in the concentrator section, along with key equipment in the recovery/MREC section, such as the sulphuric acid plant, have been completed and orders will be placed with the selected vendors shortly.

Contractor Grupo Nov has completed the civils and services connections for the initial section of the 316-person modular camp. The $1.3-million camp has been fabricated off site and is ready for shipment from Johannesburg to site during the course of March. 

All site access roads have been completed within the licence area. A 5 000 ℓ potable water tank is ready for installation to support the construction camp and the future plant facilities. 

Pensana has said that high priority is being given to community relations and, in particular, to the resettlement action and livelihoods restoration plans, which are progressing according to plan. 

Pensana has also reported that the agricultural demonstration plots are in their second year and are generating promising baseline data, providing the opportunity to train local farmers in the latest agricultural methods.

The mine and processing plant will be built from May and commissioning of the various circuits will start in March 2025, continuing until final commissioning in April 2026. 

Key Contracts, Suppliers and Consultants
ADP (main contractor); MCC (main construction); NCP International (equipment); and Grupo Nov (contractor).

Contact Details for Project Information
Pensana Rare Earths, email admin@pensana.co.uk orir@pensana.co.uk.

Edited by Creamer Media Reporter

Comments

 

Showroom

Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.09 0.142s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: