Langer Heinrich uranium restart project, Namibia – update

Image of the Langer Heinrich mine

Langer Heinrich mine

Photo by ©Bloomberg

15th November 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Langer Heinrich uranium restart project.

Location
Namib Desert, Namibia.

Project Owner/s
Langer Heinrich Mauritius Holdings is the holding company of Langer Heinrich Uranium, which holds 100% of the Langer Heinrich tenements.

Paladin Energy owns 75% of Langer Heinrich Mauritius Holdings, with 25% owned by CNNC Overseas Uranium Holdings.

Project Description
Langer Heinrich has an estimated 17-year mine life, supported by ore reserves of 84.8-million tonnes with an average uranium grade of 448 parts per million.

Life-of-mine production is estimated at 77.4-million pounds of uranium, up from a previously stated 76.1-million pounds.

Langer Heinrich was placed on care and maintenance in August 2018, owing to the sustained low uranium price.

Paladin completed a concept study in February 2019, which identified multiple options to reduce operating costs, improve process plant performance and potentially recover a saleable vanadium product.

A two-stream prefeasibility study (PFS1 and PFS2) was started in March 2019 to improve the details of the restart plan and pursue further improvement options to clearly present a compelling investment case.

PFS1 focused on confirming effective care and maintenance plans, practices and costs while developing a more detailed plan to execute a rapid restart at Langer Heinrich in an improved uranium market.

Potential Job Creation
The project will employ about 300 staff.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Paladin is forecasting total capital costs of about $125-million, from the previous forecast of $118-million.

Planned Start/End Date
The project restarted commercial production on March 30, 2024, following the successful completion of the restart project. The mine will be in operational ramp-up during the 2025 financial year, with ore feed to the plant sourced from previously mined stockpiled ore.

Production levels are expected to be higher in the second half of the year. Mining activities are expected to restart in the 2026 financial year, ahead of achieving nameplate production of six-million pounds a year by the end of 2026.

Latest Developments
Paladin has revised downwards its production forecast for the Langer Heinrich mine.

The company cited weaker-than-expected performance in October and ongoing challenges in ramping up operations as key factors behind the revised guidance.

Paladin now expects to produce between 3-million and 3.6-million pounds of uranium from Langer Heinrich in the 2025 financial year, compared with its previous forecast of 4-million to 4.5-million pounds.

Paladin has also announced a two-week planned shutdown at the mine to conduct operational improvements and upgrades aimed at addressing production challenges.

Langer Heinrich is in the midst of a 21-month ramp-up period, with the mine now about seven months into the process. 

Paladin has emphasised that production is expected to rise as the ramp-up progresses and higher-grade ore is processed in the latter half of the 2025 financial year.

“The company remains confident that, by the end of 2025, Langer Heinrich will achieve a production run rate of 6-million pounds per year,” Paladin said in a statement on November 12.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Paladin Energy, tel +61 8 9381 4366 or email paladin@paladinenergy.com.au.

Edited by Creamer Media Reporter

Comments

Latest News

Attendees at the latest AMLA workshop
Opinion: Strengthening Africa’s mining future – the crucial role of legal expertise
6th December 2024

Showroom

John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 06 December 2024
Magazine round up | 06 December 2024
6th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.051 0.091s - 129pq - 2rq
Subscribe Now