Lake Throssell sulphate of potash project, Australia

Location map of the Lake Throssel project

19th November 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Lake Throssell sulphate of potash (SoP) project.

Location
Eastern Goldfields of Western Australia.

Project Owner/s
Trigg Mining.

Project Description
Trigg has completed a scoping study that has confirmed the potential for the Lake Throssell project to be a low-cost, long-life producer of natural SoP for food production.

The project contains a total mineral resource of 1.39-million.

The development of the project comprises:

• the establishment of a trenching and bore network to supply up to 29 Gℓ a year of potassium-rich brine to the evaporation ponds for 21 years.

• 2 150 ha of evaporation ponds and a processing plant to produce 245 000 t/y of SoP;

• the supply of 2.5 Gℓ a year of process water;

• construction of supporting infrastructure;

• compaction of the product into a granular form and bagging it into one-tonne bulk bags before being packed in sea containers for transportation.


Life-of-mine production is estimated at 5.9-million tonnes grading 10.4 kg/m3  SoP.

Yearly production is estimated at 245 000 t/y SoP.

The product will be transported 350 km by road from Lake Throssell to the Malcom railhead at Leonora before being loaded on to rail and then 950 km to the container port at Fremantle.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an estimated pretax net present value, at an 8% discount rate, of $364-million and an internal rate of return of 18%, with a payback from first SoP production of 4.5 years.

Capital Expenditure
The project has a total capital cost of A$378-million.

Planned Start/End Date
Not stated.

Latest Developments
Given the results of the scoping study, the board of Trigg Mining has approved the company’s proceeding to the prefeasibility stage.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Trigg Mining, tel +61 8 6114 5685 or email info@triggmining.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.045 0.948s - 111pq - 2rq
Subscribe Now