Lac Guéret graphite project, Canada
Name of the Project
Lac Guéret graphite project.
Location
North-eastern Quebec, Canada.
Client
Mason Graphite.
Project Description
An updated feasibility study has confirmed the project’s robust economics.
Lac Guéret has proven and probable reserves of 4.74-million tonnes grading 27.8% total graphitic carbon (TGC).
The study envisages an openpit mining operation using a 100% owner-operated fleet, which has been selected to deliver an average of 190 000 t/y of mill feed that will be crushed on site and then transported on an existing road to Baie-Comeau for processing. The concentrator will produce an average of 51 900 t/y graphite concentrate over a 25-year mine life.
The ore mined is projected to yield an average grade of 27.8% TGC.
The concentrator has been designed for the standard purity of 96% TGC for the coarse products and will be capable of reaching purities of up to 97.5 % TGC for the same sizes.
Potential Job Creation
The project will create about 100 jobs.
Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of C$484-million and an internal rate of return of 27.7%, with a payback of 3.7 years.
Value
Initial capex has increased from C$200-million in the 2015 feasibility study to C$258.2-million.
Duration
The project is expected to take 13 to 16 months to complete.
Latest Developments
Early construction work is under way.
Key Contracts and Suppliers
GoldMinds Geoservices (technical and financial data).
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Mason Graphite, tel +1 647 801 7273 oremail info@masongraphite.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation