Labrador going full speed ahead with Houston development

30th October 2020

By: Marleny Arnoldi

Deputy Editor Online

     

Font size: - +

Canadian miner Labrador Iron Mines (LIM) is progressing work on Stage 2 of its planned direct shipping ore mining operations, which involves the development of the Houston project, in Labrador, Quebec.

LIM chairperson and CEO John Kearney says this decision came in light of persistently stronger iron-ore prices over the last two years, as well as increased expressions of interest from potential offtakers seeking iron-ore supply.

To assist in getting development financing, LIM has engaged Roscoe Postle Associates (RPA), which is part of SLR Consulting, to complete an independent preliminary economic assessment (PEA) on the project to be used for consideration of financing options.

LIM says RPA has extensive expertise in geological, mining and metallurgical advisory and has worked on iron-ore projects in Canada and other parts of the world before. 

The Houston deposit, and the Malcolm deposit in the area, are estimated to contain a combined measured and indicated resource of 40.6-million tonnes grading 57.6% iron.

The PEA, which should be complete before the end of the year, will focus on a higher-grade subset of this resource suitable for direct shipping using dry crushing and screening only.

LIM anticipates developing four openpits sequentially to produce an average of two-million tonnes a year of direct shipping iron-ore.

During the past several years, LIM conducted a variety of operational activities with the objective of preserving the assets of Houston, particularly around reclamation and rehabilitation of the Stage 1 mining operations, which have been in progressive reclamation since the termination of mining at the James mine, in 2014.

Last year, LIM nearly completed the rehabilitation of its Silver Yards plant site and, earlier this year, a rehabilitation programme of topsoil spreading with seeding and re-vegetation was undertaken.

LIM successfully completed its environmental regulatory requirements relating to rehabilitation of the Stage 1 James mine and associated Silver Yards site infrastructure, which paved the way for moving to Stage 2 and the development of the Houston project. 

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

Resources Watch
Resources Watch
27th March 2024

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.121 0.153s - 105pq - 2rq
Subscribe Now