Öksüt gold project, Turkey

12th June 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Öksüt gold project.

Location
Turkey.

Project Owner/s
Öksüt Madencilik Sanayi vi Ticaret, a subsidiary of Centerra Gold.

Project Description
The Öksüt project’s estimated mineral reserves as at June 30, 2015, were 26.1-million tonnes at an average grade of 1.4 g/t of gold containing 1.2-million ounces of gold using a cutoff grade of 0.3 g/t and a gold price of $1 250/oz.

The feasibility study envisions a conventional openpit and heap-leach operation. The heap-leach pad has been designed with an ultimate ore capacity of 40-million tonnes.

Electrical power is expected to be supplied to the project using a dedicated 28 km power line connected to the local power grid.

Water supply is expected to be sourced from two company-owned water wells, which have been fully permitted.

It is envisioned that a local contractor will conduct mining using a conventional truck-and-shovel fleet comprising small, selective loading equipment and 36 t trucks.

The life-of-mine (LoM) strip ratio is expected to be 2:1.

The ore will be crushed to 38 mm through two stages of crushing, and placed on the heap-leach pad at 11 000 t/d.

LoM gold recovery is expected to be 77%.

The project is expected to process 26.1-million tonnes of ore at an average grade of 1.4  g/t gold over eight years, producing 895 000 oz of gold at an average all-in-sustaining cost of $490/oz sold.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a base case net present value, at an 8% discount rate, of about $242-million and an internal rate of return of 42.5%.

Capital Expenditure
Preproduction and construction capital is expected to be $221-million, which includes a $25-million contingency.

Planned Start/End Date
Centerra expects to pour first gold from the mine in the first quarter of 2020.

Latest Developments
Centerra Gold has achieved commercial production at its Öksüt mine four months after its first gold pour.

“Commercial production at Öksüt marks a major milestone for the company. Öksüt was delivered on time and under budget,” CEO Scott Perry has said.

Key Contracts and Suppliers
None stated.

Contact Details for Project Information
Centerra Gold VP investor relations John Pearson, tel +1 416 204 1953 or email john.pearson@centerragold.com.

 

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 
ZF Aftermarket
ZF Aftermarket

ZF Aftermarket is the after-sales division of the world-renowned German ZF group, a global leader in mobility technology.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.042 0.482s - 111pq - 2rq
Subscribe Now