Aim-listed Kropz has announced an increase in the total phosphate resources to 106-million tonnes at the Elandsfontein phosphate project, in South Africa’s Western Cape province.  

However, the company had to downgrade much of the previously measured resource to indicated status and also downgrade previously indicated resources to inferred status.

The total measured and indicated resource tonnage has reduced by about 76%.

The company has been undertaking infill drilling, relogging of historical cores and mapping of ore exposures to increase the company’s level of confidence in the project, and allow for accurate and efficient mine planning.

Based on current conditions and on-site learnings, as well as revised geological interpretations, in addition to new intersections of unknown and undefined indurated phosphatic lenses during mining activity, Kropz considered it prudent that the resource model be reclassified.

“The estimate needed to be brought in line with the level of confidence that reflected grade and physical properties and continuity (mining output and plant performance), as these aspects play a role in economic viability and, therefore, associated reserve determination,” the company explains.

The updated resource now considers core recovery, average drill hole spacing and sample count. The grade has improved, with the refined lithological contacts and improved estimates from the infill drilling and pit sampling.

The Elandsfontein project’s proven reserve sits at 7.31-million tonnes grading 10.71% phosphorous pentoxide.

CEO Mark Summers says that while the downgrade of the measured and indicated resource is disappointing, it enables Kropz to move forward with a significantly increased level of confidence.

The increase in total resource and, more importantly, the increase in grade, as well as continued drilling planned for the year ahead, will further increase confidence and support in increasing reserve tonnes.

 

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
Universal Storage Systems (SA)
Universal Storage Systems (SA)

South African leader in Steel -Racking, -Shelving, and -Mezzanine flooring. Universal has innovated an approach which encompasses conceptualising,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.112 0.146s - 108pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: