Kingsrose defers production expectations at Way Linggo
PERTH (miningweekly.com) – Gold miner Kingsrose Mining on Thursday warned shareholders that it was unlikely to achieve its current production target of 20 000 oz of gold for the financial year ended June.
The reduced production came as Kingsrose experienced delays in finalising its regulatory approvals for the Way Linggo project, in Indonesia.
Final permits were expected by April this year, which would pave the way for full production to be resumed, Kingsrose said.
In July last year, the company suspended normal mining activities at the Way Linggo mine as ore production rates continued to fall.
The company took the decision to restart operations, and said on Thursday that development work was progressing well and would ensure that mining rates could be ramped up quickly once the final approvals were received.
To date, mine development has been undertaken on a limited basis, following approval of the technical and economic components of an updated feasibility report. This work was carried out while Kingsrose’s subsidiary PT Natarang Mining completed the remaining regulatory steps, which included the granting of the final forestry permit and the approval of an extension to the existing project environmental assessment to include the Talang Santo mine.
PT Natarang has requested permission to conduct full-scale mining while awaiting approval, but was advised in December by the Indonesian Mines Department that full production would only be permitted once the forestry permit and environmental assessment was granted.
Meanwhile, Kingsrose has agreed with Advanced Concept Holdings to defer the start of the repayment of a $5-million loan from January to July. The interest rate payable has been increased by 2% a year.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation