https://www.miningweekly.com
Botswana|Construction|Copper|Crushing|Engineering|flotation|Fluor|Mining|PROJECT|Resources|Road|Services|Surface|Underground
Botswana|Construction|Copper|Crushing|Engineering|flotation|Fluor|Mining|PROJECT|Resources|Road|Services|Surface|Underground
botswana|construction|copper|crushing|engineering|flotation|fluor|mining|project|resources|road|services|surface|underground

Khoemacau copper/silver project, Botswana – update

Image of Khoemacau Bosetto processing plant

Photo by Khoemacau Copper Mining

9th July 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Khoemacau copper/silver project.

Location
North-west Botswana.

Project Owner/s
Khoemacau Copper Mining (KCM), a subsidiary of Cupric Canyon Capital.

Project Description
The project entails the construction of KCM’s 3.6-million-tonne-a-year starter project, processing ore from the 91-million-tonne resource at a head grade of 2.02% copper and 21.4 g/t silver copper.

The company plans to develop the Zone 5 orebody as three separate underground mines, each producing 1.2-million tonnes a year on average for the first five years.

Each of the mines will have its own independent ramp access and operate over a strike length of about 1 000 m, extracting ore using a conventional sublevel open-stoping mining method.

The mined ore will be trucked 35 km to the Boseto processing facility, which will be refurbished and enhanced to process 3.65-million tonnes a year. Processing will be conventional sulphide flotation using three-stage crushing, ball milling and flotation, which will produce a high-quality copper concentrate grading at about 40% for shipment to African and international smelters.

The underground mine will be fully mechanised.

The project has the capacity to produce 155 000 t/y to 165 000 t/y of high-grade copper and silver concentrate, containing an estimated 60 000 t to 65 000 t of payable copper and 1.8-million to 2-million ounces of payable silver.

In addition to Zone 5 resources, there are a further 93.5-million tonnes of high-grade ore grading 1.9% copper and 33 g/t silver across the Khoemacau project. KCM plans to develop these resources in conjunction with the construction of the starter project.

The long-term plan is to expand Khoemacau to about 5.8-million tonnes a year through the expansion project, whereby a new standalone process plant will be built at Zone 5. The project is expected to produce more than 100 000 t/y of copper.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
The direct construction cost of the starter project is $397-million.

Planned Start /End Date
Underground development of Khoemacau’s Zone 5 mine started in early 2020.

KCM expects to ramp up to full production in 2022.

Latest Developments
Production of the first copper-silver concentrate from KCM’s Boseto process plant has started.

First copper concentrate was produced on June 30, 2021.

This milestone was achieved safely and within schedule, with the overall project remaining within 3% of the original budget.

The first shipment of concentrate is scheduled for July 2021. Since underground development of Khoemacau’s Zone 5 mine started, more than 350 000 t of high-grade sulphide ore has been stockpiled on surface and is available to feed the facility.

The ore is transported 35 km from the mechanised Zone 5 underground mine to the processing facility through a sealed haul road.

Key Contracts, Suppliers and Consultants
Fluor Group (engineering, procurement and construction management contract) and Ausdrill subsidiary Barminco (underground mining services contract).

Contact Details for Project Information
Cupric Canyon Capital, tel +1 480 607 6771 or email ccc@cupriccanyon.com.

Edited by Creamer Media Reporter

Comments

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
14th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.215 0.271s - 91pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: