https://www.miningweekly.com

Karma gold project, Burkina Faso

11th March 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Karma gold project, Burkina Faso.

Client
True Gold Mining.

Project Description
The feasibility study completed on the Karma project supports a heap-leach mine scenario from currently defined openpit deposits containing 949 000 oz of probable mineral reserves.

The heap-leach pad is designed to process oxide and transition ore from the five shallow pits, with a small amount of leachable sulphide ore extracted from two pits.

The two pits with the highest-grade mineral reserves will be mined first, allowing for rapid payback and strong cash flow from the outset of commercial production.

About 113.8-million tonnes of material will be mined from the five openpits over the estimated project life. This will deliver an estimated 33.2-million tonnes of ore to the process facility and 80.6-million tonnes of waste to storage facilities located near each pit. The overall strip ratio for the project is 2.43:1, with mining being conducted 350 days a year by an owner-operated fleet at total material movement rates ranging from 35 000 t/d to 45 000 t/d.

Conventional truck and shovel methods are likely to be used. Two 200 t hydraulic excavators, configured in backhoe mode, will load a fleet of ten 90 t trucks for the transport of ore and waste to the primary crusher and respective near-pit waste dumps.

Four additional 90 t trucks will deliver ore directly from the pits to the process facilities without the need for ore rehandling.

The soft nature of the openpit ore and waste material will allow for free-digging (excavated without blasting) the bulk of the material.

Twenty-five per cent of the transition ore and all the sulphide ore material will be drilled and blasted at low powder factors. This comprises only about 10% of the total material to be excavated during the mine life.

Based on the feasibility study, which excludes the North Kao deposit, five openpit areas will be developed in sequence to provide the ore feed for the heap-leach operations. These openpit mining operations will exploit the Goulagou (GGI), Goulagou II (GGII), Kao, Rambo and Nami mineral deposits. Target ore production during the life of the mine is four-million tonnes a year from no more than two openpits producing concurrently.

The Karma project’s process design is based on using conventional heap-leach technology, with a production capacity of four-million tonnes a year. Mined ore will be crushed, agglomerated and conveyed to the leach pad, where it will be stacked in two 10 m lifts and irrigated using a dilute cyanide solution. Gold dissolved by the cyanide will then be adsorbed onto activated carbon in a carbon-in-column circuit. The loaded carbon is then stripped of the gold using Zadra-type elution and the resulting product will be subjected to electrowinning and smelting to produce doré on site.

The mine will produce an average of 97 000 oz/y of gold over a mine life of 8.5 years.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 5% discount rate, of $178.2-million, and an after-tax internal rate of return of 43.1%, with payback after 1.4 years.

Value
The project requires initial capital of $131.5-million, including on-site working capital and contingency, to support the construction of a mine and associated facilities, with a process capacity of four-million tonnes a year.

Franco-Nevada and Sandstorm Gold have entered into a $120-million stream financing agreement, with True Gold Mining to assist in funding the construction of the Karma project.

Duration
First gold pour is expected in 2016.

Latest Developments
True Gold has started irrigating ore on the heap-leach pad at its Karma gold project and has reported that commissioning of the absorption, desorption and refining (ADR) plant is well under way.

The miner has indicated that the operations team is fully staffed and actively engaged in the ramp up to commercial production. The crushing, agglomerating and stacking are operating on a 24/7 schedule and has been treating ore at a rate of 600 t/h.

Meanwhile, True Gold has reported that Endeavour Mining has moved to acquire the company for its 90% interest in the project in an all-scrip deal valued at about C$191-million. The deal would create a new West Africa-focused intermediate gold producer, with a portfolio of low-cost producing assets spread across Côte d’Ivoire, Mali, Burkina Faso and Ghana.

Key Contracts and Suppliers
Senet (barrage construction, detailed engineering and construction-level design work).

On Budget and on Time?
Mining is ahead of schedule, with about 600 000 t of above-average grade stockpiled.

True Gold expects the project to pour its first gold at the end of the month.

"With gold production only weeks away and almost five months of mining under our belts, we are pleased to see mining costs tracking in-line with the feasibility study. We have purchased all key supplies and reagents and are seeing the benefits of lower prices for fuel, cement and cyanide at below feasibility cost estimates," True Gold president and CEO Christian Milau has stated.

Contact Details for Project Information
True Gold Mining, tel +1 604 801 5020 or email info@truegoldmining.com.
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.048 0.836s - 111pq - 2rq
Subscribe Now