Kapstevel South project, South Africa – update

Image of construction at the Kapstevel South project

Photo by Kumba Iron Ore

5th May 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kapstevel South (KSS) project.

Location
About 22 km from Postmasburg, in the Northern Cape, South Africa.

Project Owner/s
Anglo American subsidiary Kumba Iron-Ore.

Project Description
KSS is a four-million-tonne-a-year, high-grade iron-ore replacement project.

The project entails the development of a new pit ­– KSS – and associated infrastructure at Kolomela to sustain output of about 12-million tonnes a year and extend the remaining life-of-mine to 2034.

The pit is a conventional truck-and-shovel operation producing high-quality direct shipping ore. 

Potential Job Creation
The project will enable Kolomela to sustain the current workforce until 2034 and, therefore, avoid the job losses that would have started from 2027 if the project was not approved and executed.

Net Present Value/Internal Rate of Return
It is expected that the addition of the KSS pit will deliver an after-tax internal rate of return of about 25% and an earnings before interest, taxes, depreciation and amortisation margin of more than 35%.

Capital Expenditure
Capital expenditure for the project is estimated at R7-billion.

Planned Start/End Date
The project was approved in July 2020. Pit establishment and waste stripping started in 2021. The infrastructure construction is on track and will be completed by the fourth quarter of 2023. First ore is expected to be delivered in the first half of 2024.

Latest Developments
The project is more than 67% complete, while 29 heavy mining machines have also been procured. The focus is now on waste-stripping activities to deliver first ore early in the first half of 2024.

Key Contracts, Suppliers and Consultants
In support of Anglo American’s drive to develop local communities, the project has allocated more than R1.7-billion to host community contractors involved in the construction and mining scope of the project.

Contact Details for Project Information
Anglo American (media), Sinah Phochana, tel +27 12 683 7019 or email sinah.phochana@angloamerican.com.
Anglo American (investors), Penny Himlok, tel +27 12 622 8324 or email penny.himlok@angloamerican.com.             

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.045 1.211s - 111pq - 2rq
Subscribe Now