Kangala thermal coal project, South Africa
Name and Location
Kangala thermal coal project, Mpumalanga, South Africa.
Client
Universal Coal.
Project Description
Kangala has proven reserves of 20.8-million tonnes of thermal coal. It comprises three properties – Wolvenfontein, Middelbult and Modderfontein.
Saleable coal tonnages averaging 2.1-million tonnes a year will be achieved from a 2.4-million-tonne-a-year run-of-mine production rate over the life of the mine, which is forecast at 8.5 years.
Value
A$46.8-million. All funding for the project has been secured.
Duration
Kangala will begin production in February 2014.
Latest Developments
Universal Coal has started hot commissioning at its Kangala operations, with first production on track for this month.
Cold commissioning of the processing plant was successfully completed in December, enabling the company to proceed with its ramp-up plans.
Universal Coal has noted that the boxcut operation continues to progress well, with coal being mined and sent to the run-of-mine stockpiles over the past three months.
The majority of this stockpile will now be used in the hot commissioning of the crushing and screening plant.
The Kangala project is scheduled to produce about 200 000 t/m by March this year.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Universal reports that the A$46.8-million project remains on budget and is set to deliver its first production by February.
Contact Details for Project Information
Universal Coal, tel +27 12 460 0805, fax +27 12 460 2417 or email info@universalcoal.co.za.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation