Name and Location
Jambreiro iron-ore project, Brazil.

Client
Centaurus Metals.

Project Description
The project is based on a Joint Ore Reserves Committee-compliant resource of 125-million tons, grading 26.7% iron.

The ore reserve will provide 18-million tons of high-grade, low-impurity sinter blend concentrate – enough to underpin nine years of production at an initial two-million-tons-a-year production rate.

Value
The project has a preproduction capital estimate of A$136-million.

Duration
The company’s project execution plan centres on the start of on-site construction that will immediately follow the receipt of an installation licence, expected in April 2013. Construction is expected to take eight months, by which time the company is expected to have been granted its mining lease, enabling it to start full-scale production.

Latest Developments
Centaurus Metals has secured a key installation licence for its Jambreiro project, clearing the way for on-site construction to start.

The granting of the licence was achieved ahead of schedule and follows the approval of the project’s environmental control plans.

The licence marks the final regulatory milestone reached to start construction.

Initial development work is already under way and actual works are scheduled to start at the end of April, subject to the completion of suitable offtake arrangements and the finalisation of the overall funding mix.

The installation licence allowed Centaurus to operate at a production rate of three-million tons a year of saleable product, although the company has previously said it would start production at an initial rate of two-million tons a year.

Key Contracts and Suppliers
MCA Auditoria e Gerenciamento (MSC) and Tetra Tech (EP).

On Budget and on Time?
Centaurus MD Darren Gordon says that the team in Brazil continues to deliver against the company’s timetable and it continues to work its way towards production by the end of the year, “systematically ticking all of the boxes required to allow the Jambreiro development to move ahead on time.”

Contact Details for Project Information
Centaurus Metals, tel +61 8 9420 4000, fax +61 8 9420 4040 or email office@centaurus.com.au.
MCA Auditoria e Gerenciamento, tel +55 31 2127 6800 or email comunicacao@mca.srv.br.
Tetra Tech, tel +1 626 351 4664, fax +1 626 351 5291 or email info@tetratech.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.042 0.107s - 111pq - 2rq
Subscribe Now