Jambreiro iron-ore project, Brazil

15th March 2013

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Jambreiro iron-ore project, Brazil.

Client
Centaurus Metals.

Project Description
The project has a Joint Ore Reserves Committee-compliant reserve of 48.5-million tons at an average grade of 28.1% iron for the friable component of the Jambreiro resource.

The ore reserve will provide 18-million tons of high-grade, low-impurity sinter blend concentrate – enough to underpin nine years of production at the planned two-million-ton-a-year production rate.

Value
The project has a preproduction capital estimate of A$136-million.

Duration
The company’s project execution plan centres on  the start of on-site construction that will immediately follow the receipt of an installation licence, expected in April 2013. Construction is expected to take eight months, by which time the company is expected to have been granted its mining lease, enabling it to start full-scale production.

Latest Developments
Centaurus has awarded the detailed engineering and procurement (EP) contract for the implementation of the project to Tetra Tech.

The award of the EP contract follows the recent award of the management support contract (MSC) to MCA Auditoria e Gerenciamento.

The award of the contract is consistent with Centaurus’ development schedule for the Jambreiro project and will ensure the issue of sufficient detailed construction drawings and work scopes to allow for the mobilisation of civil construction contractors to site, on approval of the final installation licence, which is expected in April 2013.

Meanwhile, discussions to secure finance for Jambreiro are progressing well, with a final investment decision and commitment to the full capital budget to be delivered upon finalisation of the overall funding mix.

Key Contracts and Suppliers
MCA Auditoria e Gerenciamento (MSC) and Tetra Tech (EP).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Centaurus Metals, tel +61 8 9420 4000, fax +61 8 9420 4040 or email office@centaurus.com.au.
MCA Auditoria e Gerenciamento, tel +55 31 2127 6800 or email comunicacao@mca.srv.br.
Tetra Tech, tel +1 626 351 4664, fax +1 626 351 5291 or email info@tetratech.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.043 0.81s - 111pq - 2rq
Subscribe Now