Ivanhoe Mines records strong second-quarter at Kamoa-Kakula
Canadian miner Ivanhoe Mines’ Kamoa-Kakula copper complex, in the Democratic Republic of Congo (DRC), sold 101 526 t of payable copper in the second quarter ended June 30 and recognised record quarterly revenue of $702-million and earnings before interest, taxes, depreciation and amortisation (Ebitda) of $457-million.
Ivanhoe recorded adjusted Ebitda of $172-million for the quarter, compared with $101-million for the same period in 2022.
Kamoa-Kakula’s quarterly cost of sales totalled $1.24/lb of payable copper, while C1 cash costs were $1.41/lb, at the lower end of guidance.
Ivanhoe recorded a profit of $87-million for the quarter, net of a $27-million non-cash loss on the $575-million convertible bond fair valuation, compared with a profit of $82-million for the previous quarter.
Since entering Phase 1 commercial production on July 1, 2021, the Kamoa-Kakula joint venture has generated $1.82-billion of net cash from operating activities, which has funded both the Phase 2 and Phase 3 expansions to date.
Ivanhoe has a strong balance sheet with cash and equivalents of $393-million on hand as at June 30, and expects Kamoa-Kakula’s Phase 1 and Phase 2 cash flow to be sufficient to fund the Phase 3 expansion capital cost requirements at current copper prices.
OPERATIONAL HIGHLIGHTS
Record quarterly production of 103 786 t of copper in concentrate was achieved at Kamoa-Kakula for the quarter, compared with 93 603 t in the previous quarter and 87 314 t in the previous year’s second quarter.
Over the first six months of the year, Kamoa-Kakula produced 197 389 t of copper in concentrate, placing it well on track to deliver yearly production guidance of between 390 000 t and 430 000 t of copper.
Kamoa-Kakula's Phase 1 and 2 concentrators milled a record 2.2-million tonnes of ore during the second quarter at an average feed grade of 5.2% copper. This included high-grade, run-of-mine ore from the Kakula mine, supplemented with ore from the surface stockpiles to achieve throughput higher than original design capacity.
Kamoa-Kakula's Phase 3 mine and concentrator expansion, 500 000 t/y on-site, direct-to-blister copper smelter and the refurbishment of Turbine No 5 at the Inga II hydroelectric facility are advancing on schedule and are expected to be complete in late 2024.
At current copper prices, it is expected that cash flow from Kamoa-Kakula’s Phase 1 and 2 operations will be sufficient to fund the remaining 2023 and 2024 expansion capital cost requirements of about $2.1-billion.
Ivanhoe continues its expansive copper exploration programme on its Western Foreland licences adjacent to Kamoa-Kakula. The 2023 exploration programme is budgeted at about $19-million.
A total of 37 holes and 10 853 m were completed during the quarter following the conclusion of the wet season in May. A total of 15 736 m of diamond core have been drilled in the first half of the year.
Ivanhoe is on schedule to publish a maiden mineral resource estimate for its Makoko and Kiala high-grade copper discoveries in the Western Foreland in the next quarter.
Ivanhoe is undertaking optimisation work to identify value-accretive options for installing hoisting capacity to Platreef's Shaft 3, which was originally planned as a ventilation and secondary escape shaft.
The additional hoisting capacity from Shaft 3 may be used to accelerate underground mining activities for Phase 2, in advance of the completion of Shaft 2, which is expected in 2027.
At the Kipushi zinc/copper/lead/germanium mine in the DRC, which the company is restarting, overall construction progress is about 50% complete and construction of the concentrator is on schedule for commissioning in the third quarter of 2024.
Kipushi's underground development activity is ahead of schedule, with 2 147 m of lateral development completed since September 2022.
Stoping of the ultrahigh-grade Big Zinc orebody is expected to begin in January 2024.
The year-to-date underground development rate averages about 250 m a month. The underground development rate is expected to increase to about 450 m a month by year-end.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation