https://www.miningweekly.com

Independent studies confirm Toro hopes

30th January 2014

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – An independent scoping study and a preliminary economic assessment have confirmed uranium developer Toro Energy’s expected improvements on the Wiluna project, in Western Australia, following the incorporation of the Lake Maitland deposit into the project.

Based solely on mining the already-approved Centipede and Lake Way deposits, the Wiluna project was expected to have a mine life of 16 years with average production of two-million pounds of uranium oxide (U3O8) a year, for the first ten years of operation.

Total production over the life of the mine would reach 30.2-million pounds of U3O8.

“The new results validate Toro’s project development work in 2013, in particular the drilling that delivered resource upgrades at each of Centipede, Millipede and Lake Way, as well as the acquisition of Lake Maitland,” said Toro MD Vanessa Guthrie.

She pointed out that the studies had also shown that under suitable market conditions, lower cutoff grades would allow the exploitation of the 200 parts per million cutoff resource at these deposits.

“Moreover, there remains further upside potential at Wiluna, as the mining study does not include the indicated and inferred resource at the project’s Dawson Hinkler and Nowthanna deposits, which could extend the total mine life well beyond 20 years.”

Guthrie added that the study results were achieved without affecting the processing facility throughput or development approvals at the Centipede and Lake Way deposits.

She said the company’s immediate priority now was to refer the Millipede and Lake Maitland deposits for state and federal environmental assessment.

“During 2014, Toro will pursue the further necessary government environmental approvals and progress funding arrangements with potential partners to underpin project financing and project offtake agreements.”

Meanwhile, Toro has also determined that an additional A$27-million in capital would be required for the Wiluna project to acquire and operate a mining fleet under an owner-operator model.

While the total capital costs for the project would be confirmed during the definitive feasibility study, previous estimates have placed the capital cost at between A$207-million and A$269-million, if the engineering, procurement, construction and management costs were included.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 
AirNox Pty Ltd
AirNox Pty Ltd

AirNox (Pty) Ltd is a level 1 BBBEE manufacturer of complete AdBlue® solutions for operators of SCR diesel engines and AUS40 across South Africa...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.059 1.231s - 110pq - 2rq
Subscribe Now