Impala No 16 Shaft project, South Africa
Name and Location
Impala No 16 Shaft project, North West, South Africa.
Client
Impala Platinum (Implats).
Project Description
The shaft development is situated on the south-east corner of the Impala mining lease down dip of No 1 Shaft, on the western limb of the Bushveld Complex. The No 16 Shaft is expected to produce 226 500 t/m of reef from seven operational levels. The shaft will access the Merensky and upper group two (UG2) reef horizons.
The No 16 Shaft ore reserves will be accessed by a downcast rock and men-and-materials shaft.
The rock and men-and-materials shaft is lined to an inside diameter of 10 m and sunk to 1 648 m, while the ventilation shaft is a 6.8-m-diameter inside-concrete lining shaft, sunk to 1 390 m below the surface.
As the shaft will access reef from a depth of 1 220 m to 1 540 m, full-time refrigeration, introduced through the rock and men-and-materials shaft, will be required for the underground workings, . The refrigeration is designed to ventilate a maximum of 900 kg/s of cooled air from the surface.
The No 16 Shaft headgear, with a structural height of 108 m, houses two Koepe winders. One will hoist personnel and material, while the other will hoist only rock. The rock hoist tipping arrangement will be located inside the concrete headgear to reduce noise pollution. A conveyor will transfer reef and waste from the headgear bins to a transfer tower, from where reef will be transferred to two concrete silos – one for Merensky and one for UG2.
The power requirements for the new shaft will be met from a new Eskom 88/33 kV yard at the No 15 Shaft.
Value
R6.9-billion.
Duration
Production is expected to start in 2014.
Latest Developments
Implats has reported that No 16 Shaft remains on schedule to start production in 2014, with an output of 15 000 oz/y of platinum.
The build-up to full throughput of 2.7-million tonnes a year, yielding 185 000 oz of platinum, is scheduled for 2018.
Key Contracts and Suppliers
Shaft Sinkers (shaft sinking); Read Swatman & Voigt (engineering, procurement and construction management); JJG Construction (civil works – Phase 2); Louwill Engineering (structural steel – Phase 2); NIC Instruments & Engineering (electrical – Phase 2); FLSmidth Minerals (Koepe winder – mechanical); ABB South Africa (Koepe winder – electrical); and Wade Walker (surface electrical works).
On Budget and on Time?
The project is on target for the start of production during the third quarter of 2013.
Contact Details for Project Information
Impala No 16 Shaft general manager Frikkie Höll, tel +27 82 802 5051; or project manager Jako Pienaar, tel +27 72 699 9373 or email jako.pienaar@implats.co.za.
Shaft Sinkers, +27 11 445 4300.
JJG Construction, tel +27 18 484 1427, fax +27 18 484 5017 or email info@jjg.co.za.
Louwill Engineering, tel +27 11 818 5844.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation