https://www.miningweekly.com

Houndé gold project, Burkina Faso

1st June 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Houndé gold project.

Location
The project is located within the Birimian greenstone belt in Burkina Faso, just south of Semafo’s Mana mine and about 250 km south-west of the capital city, Ouagadougou, and benefits from excellent existing infrastructure.

Client
Houndé Gold Operation, Endeavour Mining’s Burkina Faso operating subsidiary.

Project Description
With its robust grade and low cash costs, Houndé ranks among West Africa’s highest-quality gold development projects.

Once in full production, Houndé is expected to become Endeavour’s flagship low-cost operation, with a life-of-mine of more than ten years.

Endeavour Mining expects to produce an average of 190 000 oz/y at an all-in sustaining cost (AISC) of $709/oz over the life-of-mine. Over its first four years, Houndé’s average production is expected to be 235 000 oz/y at an AISC of $610/oz.

A 34% increase in the estimated mineral reserve has resulted in greater output expectations and a longer mine life.

The project has proven and probable reserves of 30.6-million tonnes, with an average grade of 2.1 g/t gold.

The updated mine plan defines a large-scale openpit mine that provides 29.7-million tonnes of ore at 2.15 g/t of gold and 251-million tonnes of waste for a strip ratio of 8.4:1.

The enhanced production, relative to the November 2013 feasibility study, is a result of the exploration additions from 2014 and an optimisation of the mine plan to access high-grade and shallow gold-mineralisation during the initial years of the mine life.

The processing plant consists of a three-million-tonne-a-year gravity circuit/carbon-in-leach (CIL) plant with a semiautogenous (SAG) ball crushing comminution circuit.

Additional infrastructure includes the construction of the 38-km-long, 91 kV overhead power line.

Exploration potential
The Houndé exploration tenement covers more than 1 075 km2 within the highly prospective Birimian greenstone belt. Following a two-year period of no drilling, exploration activities will resume in 2017, with a $5-million programme totalling an estimated 45 000 m.

The focus will be on delineating high-grade targets, such as Bouere and Kari Pump, in addition to performing reconnaissance drilling.

Openpit prestrip mining at the main Vindaloo openpit, adjacent to the processing facility, also started in late 2016.

The enlarged reserve will result in total gold production of about 1.9-million ounces over a ten-year mine life, compared with the originally estimated 1.4-million ounces over an eight-year mine life.

Potential Job Creation
More than 2 000 personnel, including contractors, are on site, more than 94% of whom are Burkinabe.

Net Present Value/Internal Rate of Return
The internal rate of return has increased from the previously estimated 22.4% to 32% at a gold price of $1 250/oz.

The project’s after-tax net present value has been estimated at $359-million at the same gold price.

Value
The updated capital cost is estimated at $328-million, including contingency, working capital and import duties.

This represents a 3.2% increase over the $315-million estimate in the November 2013 feasibility study.

Duration
The Houndé mine began processing ore ahead of schedule on September 25 and achieved its first gold pour on October 18.

Latest Developments
Endeavour Mining has discovered two new large mineralised zones – Kari Centre and Kari West – at its Houndé mine.

Following the Kari Pump discovery in December last year, exploration efforts were prioritised on the wider Kari area, which hosts a large gold-in-soil geochemical anomaly covering a 6-km-long by 2.5-km-wide area.

More than 1 000 holes comprising 76 000 m have been drilled in the Kari area since late December, extending the mineralised zone to a very large area, now measuring 4 km long and 3 km wide, with about 25% of the gold-in-soil anomaly remaining to be drilled. 

"With Houndé ramped up and the plant performing above nameplate capacity, we are eager to pursue additional upside from exploration. These new discoveries provide confidence in achieving our strategic objective of maintaining a steady production profile at an attractive all-in sustaining cost over at least ten years,” CEO Sebastien de Montessus has said.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
The project has been completed ahead of schedule and below budget.

Contact Details for Project Information
Endeavour Mining, tel +44 203 640 8665 or email info@endeavourmining.com.
 
 
 

 

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.042 0.968s - 111pq - 2rq
Subscribe Now