Heron awards A$107m Woodlawn contract

4th May 2017

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – ASX-listed Heron Resources has awarded a A$107-million engineering, procurement and construction contract to project house CIMIC for the 1.5-million-tonne-a-year mineral processing plant and associated infrastructure at the Woodlawn base metals project, in New South Wales.

“This contract award follows the successful undertaking of a front-end engineering design programme that included a value engineering approach incorporating significant improvements on the earlier feasibility study work,” said Heron MD and CEO Wayne Taylor.

“The nature of this contract, which included guaranteed maximum price and performance incentives, aligning CIMIC and Heron in delivering an under-budget and early result.”

Work on the contract is expected to start in mid-2017.

Heron, meanwhile, said that full project engineering is around 20% complete, and on-site work is scheduled to start immediately following the completion of project financing.

Woodlawn is expected to produce 40 000 t/y of zinc, 10 000 t/y of copper and 12 000 t/y of lead, over an initial mine life of 9.3 years, with potential to extend the mine life to more than 11.5 years.

The project will process one-million tonnes a year from underground mining and up to 1.5-million tonnes a year from reclaiming tailings, with two production sources providing operational flexibility and reducing risk.

Heron is hoping to start production in 2018.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rio-Carb
Rio-Carb

Rio Carb is an OEM (Original Equipment Manufacturer) of R-C700 Chromium Carbide (CrC) alloy clad wear plates and pipes used for heavy materials...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.044 0.243s - 110pq - 2rq
Subscribe Now