Name of the Project
Hawsons iron project.

Location
The project is located near Broken Hill, in New South Wales, Australia.

Client
Carpentaria Exploration.

Project Description
A prefeasibility study completed on the project has shown it to have robust economics for the production of ten-million tonnes a year of Hawson’s Supergrade, with a product specification of 69.9% iron for a mine life of 20 years. The ore is to be mined and processed on site, with the final mineral concentrate being transported by slurry pipeline to a rail head site near Broken Hill.

The truck-and-shovel mining method will be used for the prestripping and the early mine plan, while in-pit conveying (IPC) will be used in Year 5 once meaningful depths have been reached. The plan is to use the conveyor for the vertical lift and the trucks for horizontal movement, maximising the use of comparatively cheap electrical power, reducing truck hours and improving safety.

Following a prestrip of about 150-million tonnes, the life-of-mine waste:ore ratio is 0.40, dropping to near zero by Year 11.

A total of 1.41-billion tonnes of ore and 568-million tonnes of waste are mined after prestripping. A maximum mining rate of 152-million tonnes a year is expected to be achieved in Year 7. All major processing will occur in the magnetite concentrator at the mine site before transporting the concentrate in slurry form to the railhead for dewatering. Tailings will be thickened and pumped to a circular tailings storage facility, and single cell and perimeter discharge will be used.

Jobs to Be Created
Not stated.

Net Present Value/Internal Rate of Return
The project has a post-tax net present value, at a 10% discount rate, of $1.09-billion and an internal rate of return of 17.8%.

Value
Preproduction costs have been estimated at $1.4-billion.

Duration
Not stated.

Latest Developments
None stated.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Carpentaria Exploration, tel +61 7 3220 2022 or email info@capex.net.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

North Ridge Pumps
North Ridge Pumps

North Ridge Pumps is an independent manufacturer of pumps. We have a proven track record for product support and customer service throughout the...

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.044 0.658s - 111pq - 2rq
Subscribe Now