Hamersley iron project, Australia
Name and Location
Hamersley iron project, Australia.
Client
Winmar Resources and Cazaly Resources.
Project Description
A scoping study on the Hamersley project has indicated that the project is economically viable.
Based on the current mineral resource of 42.6-million tonnes, at 55.2% iron, the project could sustain an initial two-million-tonne-a-year direct shipping ore (DSO) project.
According to the scoping study, the DSO project will operate for the first three to four years, after which a wet beneficiated fines ore process, with a capacity for about two-million tonnes a year, will be introduced for the remainder of the 14-year mine life.
Value
The initial DSO project will allow for a lower initial capital requirement and present a lower risk profile to develop the deposit, while also offering access to a larger number of contractors that can operate at the proposed capacity.
Revenue generated from the DSO project will be used to fund the wet processing plant upgrade.
Duration
Not stated.
Latest Developments
Winmar is expected to launch a scoping study on the infrastructure requirements for its Hamersley project.
The infrastructure scoping study will prove up the economic viability of transporting the iron-ore from mine gate to a suitable port facility and will examine transportation options that include a combination of road and rail, in conjunction with available port infrastructure options.
Together with the Hamersley scoping study, the infrastructure study will provide the project partners with key information that will assist partners in identifying and collaborating on strategic infrastructure solutions.
The infrastructure study was expected to take five to six weeks to complete.
Meanwhile, Winmar has initiated a prefeasibility study on the Hamersley project. Metallurgical testwork is also planned to confirm the processing parameters and to possibly upgrade the resource.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Winmar Resources, tel + 61 2 9020 4000, fax + 61 2 9020 4190 or email info@winmarresources.com.au.
Cazaly Resources, tel +61 8 9322 6283, fax +61 8 9322 6398 or email admin@cazalyresources.com.au.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation