Gruyere gold project, Australia

19th October 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Gruyere gold project.

Location
The project is located in the Yamarna greenstone belt, about 200 m east of Laverton, in Western Australia.

Client
The project is a joint venture (JV) between Australia’s Gold Road Resources and South Africa’s Gold Fields.

Gold Road and Gold Fields entered into a 50:50 JV over the Gruyere project in November 2016. The South Africa-based major paid A$350-million for its share in the project.

Project Description
A feasibility study has confirmed it as one of the longest-life, lowest-cost undeveloped gold deposits in the world, with an estimated mine life of 15 years.

The project has total proven and probable reserves of 91.6-million tonnes grading 1.2 g/t gold. The Gruyere JV has also awarded mining leases over additional mineral resources at Central Bore and Attila-Alaric, which do not form part of the Gruyere project feasibility study.

Development of the project is based on one large openpit mine and a conventional semiautogenous/ball mill circuit, gravity/carbon-in-leach (CIL) plant, with throughput of 7.5-million tonnes of fresh ore a year and up to 8.8-million tonnes of oxide ore a year.

A mining contractor will undertake activities, with Gold Road providing technical and managerial direction.

The feasibility study proposes that the pit be mined in four stages. Stages 1 and 2 comprise two independent pits in the northern and southern ends of the deposit. Stage 3 will combine the two starter pits and Stage 4 will cut back to the final pit design.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value (NPV), at an 8% discount rate, of A$486-million and an internal rate of return (IRR) of 24% at a A$1 500/oz gold price. At a A$1 750/oz gold price, the NPV increases to A$910-million, with an IRR of 35%.

Value
In July 2018, an independent third-party review of the definitive estimate for the Gruyere gold project has increased the capital cost estimate to A$621-million, up from the previous budget of A$532-million.

The updated capital cost included scope changes and force majeure costs of A$30-million, as well as a A$30-million contingency.

Key contributors to the increased capital cost included a range of scope changes that will improve the operability and maintainability of the process plant and infrastructure, as well as advancing operating and capital expenditure, including the buying of additional equipment previously intended to be hired.

Costs will be funded from existing cash and working capital facilities.

Duration
The project’s execution is based on a five-month early works programme, immediately followed by a 24-month construction and commissioning timeframe to achieve first gold production by the end of 2018.

Latest Developments
The Gruyere gold project remains on schedule to produce its first gold in the June quarter of next year.

Overall project engineering on the project was about 96% complete at the end of the September quarter, while project construction was 71% complete.

The first-stage run-of-mine pad civil works have also been completed, with assembly started on the primary crusher.

Meanwhile, the mining fleet and operations team mobilisation is in progress, and mining operations are expected to start in November.

“Construction of the Gruyere gold project and preparations for the commencement of operations are progressing well,” Gold Fields executive VP for Australia Stuart Mathews has said.

Key Contracts and Suppliers
Amec Foster Wheeler and Civmec (EPC), APA Group (pipeline and gas-fired power station), MACA (airstrip) and MACA and ACJV (Yeo borefield construction), Amec Foster Wheeler Civmec JV (EPC contractor).

On Budget and on Time?
First gold from the Gruyere project remains on schedule for the June quarter of 2019.

The capital cost of the project, however, has increased to A$621-million.

Contact Details for Project Information
Gold Road Resources, tel +61 8 9200 1600, fax +61 8 9481 6405 or email perth@goldroad.com.au.

 

 

 

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.046 1.012s - 111pq - 2rq
Subscribe Now